INSP-Final Inspection | 5/13/2005 | 5/13/2005 | 5/13/2005 | P | PASS |
Troy Cobbley
|
|
|
Fire sprinkler finaled
|
INSP-Supply line flush | 5/3/2005 | 5/4/2005 | 5/4/2005 | A | PASS |
Troy Cobbley
|
|
|
Underground flush and forward flush passed
|
INSP-Sprinkler Rough-in/Hydro | 10/20/2004 | 10/21/2004 | 10/21/2004 | A | PASS |
Troy Cobbley
|
|
|
Undergrond hydro test passed 10/21/2004 12:16:39 PM
|
INSP-Sprinkler Rough-in/Hydro | 10/20/2004 | 10/20/2004 | 10/20/2004 | A | PASS |
Troy Cobbley
|
|
|
Remaining underground supply piping is ok to cover. Dave Miller has given Shilo the ok to have the underground partialy covered by the building slab and the stub-in relocated from the electrical room to the hot water heater room. 10/20/2004 7:57:39 AM
|
Sprinkler Plan Check | 10/14/2004 | | 10/15/2004 | | PASS |
Bill Alexander
|
|
|
Per Dave Miller approval (plan signed).
|
Miscellaneous action | | | 10/15/2004 | | DONE |
|
|
|
Took plans to permit desk for calling and issueing.
|
Meeting | | | 10/15/2004 | | DONE |
|
|
|
2:30 Meeting with Bill Alexander, Dave Miller, Trent Bice and Randy Knudsen regarding the installation of underground under the footing and then 9'-0" of slab to a relocated room/location in this structure.
|
(F) Reprint permit | | | 10/15/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/15/2004 | | 10/15/2004 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/14/2004 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 10/12/2004 | 10/13/2004 | 10/13/2004 | A | CANC |
Troy Cobbley
|
|
|
Forrest is the formeman on site. This is for an underground inspection.; Phone #: ###-#### Internet Inspection Request from: Trent Bice
|
INSP-Sprinkler Rough-in/Hydro | 10/13/2004 | 10/13/2004 | 10/13/2004 | P | PART |
Troy Cobbley
|
|
|
Underground supply line is ok to cover to 20 feet past the 90 bend. Resubmittal is required since piping was not installed as shown on the approved plans. Piping is run under slab to a new location. 10/13/2004 2:16:59 PM
|
Permit Ready to Issue | | | 9/17/2004 | | DONE |
|
|
|
|
Telephone call | | | 9/17/2004 | | DONE |
|
|
|
Spoke with Don and told him that permit is ready & fees///9/17/04 8:33am BAS
|
Issue and Print Permit | | | 9/17/2004 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 9/8/2004 | | 9/16/2004 | | DONE |
|
|
|
|
Sprinkler Plan Check | 9/8/2004 | | 9/16/2004 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/16/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/16/2004 | | 9/16/2004 | | DONE |
|
|
|
|
Application received | | | 9/8/2004 | | |
|
|
|
|