INSP-Final Inspection | 2/22/2005 | 2/22/2005 | 2/22/2005 | P | PASS |
Troy Cobbley
|
|
|
Fire sprinkler finaled 2/22/2005 4:04:36 PM
|
DOC - Permit Finaled | 2/22/2005 | 2/22/2005 | 2/22/2005 | P | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 2/22/2005 4:04:40 PM
|
Miscellaneous action | | | 2/15/2005 | | DONE |
|
|
|
Recieved fax submittal on changing out the RP Backflow from the Ames to a Febco RP.
|
Plan resubmittals received | | | 2/14/2005 | | DONE |
|
|
|
|
INSP-Final Inspection | 2/4/2005 | 2/7/2005 | 2/7/2005 | P | FAIL |
Troy Cobbley
|
|
|
Provide test papers and repair the inconsistant flow alarm for the DBSI riser. 2/7/2005 4:28:12 PM
|
INSP-Sprinkler Rough-in | 1/6/2005 | 1/7/2005 | 1/7/2005 | A | PART |
Troy Cobbley
|
|
|
Forward flush for the new backflow preventors and the final hydro test passed. Corrections have been made to all items previously listed except for items in DBSI's tenant space. Need test papers from contractor. 1/7/2005 11:41:38 AM
|
INSP-Sprinkler Rough-in/Hydro | 1/6/2005 | 1/6/2005 | 1/6/2005 | P | PART |
Troy Cobbley
|
|
|
kerry -call 1st before insp ; Phone #: ###-#### Overhead hydro test for the canopy at Blockbuster and the DBSI canopy passed. Overhead hydro test for the canopy in front of Rite Aid failed. 1/6/2005 3:23:13 PM
|
INSP-Sprinkler Rough-in | 12/28/2004 | 12/29/2004 | 12/29/2004 | A | PART |
Troy Cobbley
|
|
|
Sprinkler rough-in ok except for compliance with notes 89 and 91of review comments, hangers on bottom chord and hung on a single truss. Piping in canopies is allso laying on the bottom chord. This needs changed or provide engineering verification. Pipe straps in the canopies are spaced up to 22' apart in some locations. 18' in others. This does not meet nfpa 13 table 9.2.2.1. Provide canopies that are missing. Lower pendant in dbsi's office as shown on plans. Replace bent pendants in dbsi's space. Relocate pendants that are too close to wall in dbsi's space. Complete all other items on review notes such as forward flush, hydro test ect. 12/29/2004 11:12:24 AM
|
Issue and Print Permit | | | 12/22/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/10/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/10/2004 | | 12/10/2004 | | DONE |
|
|
|
|
Telephone call | | | 12/10/2004 | | DONE |
|
|
|
left vm Tom Easton - ###-#### that permit and fees are ready to be picked up
|
Telephone call | | | 12/10/2004 | | DONE |
|
|
|
lft vm tom easton that permit and fees are ready to be picked up
|
Plan assigned to (Bill) | 12/2/2004 | | 12/9/2004 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/2/2004 | | 12/9/2004 | | PART |
Bill Alexander
|
|
|
A. Provide a copy (or copies) of the companies contract documents relating to the final accepted bids/prices settlement (include all change orders, extras, etc., for verification of BCO ยง4-02-28(2-B) which reads: "When the installation of sprinkler heads is not involved or insignificant due to the type of work being permitted, a plan review fee equivalent to 1.05% of the total bid price shall be assessed, up to a maximum of $3,150 (whichever is larger), and paid to the building official."
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/9/2004 | | DONE |
|
|
|
|
Plan resubmittals received | | | 12/2/2004 | | |
|
|
|
|
Issue permit | | | 11/15/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/12/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/12/2004 | | 11/12/2004 | | DONE |
|
|
|
|
Telephone call | | | 11/12/2004 | | DONE |
|
|
|
Left message for Tom that permit is ready & fees///11/12/04 9:30am BAS
|
Plan assigned to (Bill) | 9/30/2004 | | 11/10/2004 | | DONE |
|
|
|
|
Sprinkler Plan Check | 10/27/2004 | | 11/10/2004 | | PART |
Bill Alexander
|
|
|
Need resubmittal-refer to review notes.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/10/2004 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/27/2004 | | DONE |
|
|
|
|
Telephone call | | | 10/18/2004 | | DONE |
|
|
|
Spoke with Tom and told him that plans failed and needed picked up///8:55am 10/18/04 BAS
|
Sprinkler Plan Check | 10/1/2004 | | 10/15/2004 | | FAIL |
Bill Alexander
|
|
|
The data has been moved to a Word document attached to this case.
|
Miscellaneous action | | | 10/15/2004 | | DONE |
|
|
|
Returned plans/documents to permit desk for returning.
|
INSP-Final Inspection | 10/4/2004 | 10/4/2004 | 10/4/2004 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with dave millers and teresa's permission until the fire alarm and fire sprinklering of the outside canopies have been finished
|
Application received | | | 9/30/2004 | | |
|
|
|
|