INSP-Final Inspection | 9/2/2005 | 9/2/2005 | 9/2/2005 | P | PASS |
Forrest France
|
|
|
Underground fire supply line permit finaled.
|
INSP-Sprinkler Rough-in | 7/15/2005 | 7/19/2005 | 7/19/2005 | A | FAIL |
Troy Cobbley
|
|
|
Inspection was for the cpvc piping in the existing areas. Wrong pendants installed. Will need to verify esch. for pendants. Need to provide eq. bracing for the cpvc mains.
|
INSP-Sprinkler Rough-in/Hydro | 4/19/2005 | 4/20/2005 | 4/20/2005 | P | PASS |
Forrest France
|
|
|
Underground fire supply line hydro OK.
|
INSP-Supply line flush | 4/1/2005 | 4/4/2005 | 4/4/2005 | A | FAIL |
Forrest France
|
|
|
Fail, discharge hose too small to obtain required flow.
|
INSP-Sprinkler Rough-in/Hydro | 1/7/2005 | 1/7/2005 | 1/7/2005 | P | PART |
Troy Cobbley
|
|
|
Remaining underground supply piping from the stake to the previously approved stub out is ok to cover 1/7/2005 3:08:40 PM
|
INSP-Sprinkler Rough-in | 1/6/2005 | 1/6/2005 | 1/6/2005 | P | PART |
Troy Cobbley
|
|
|
Underground supply piping is ok to cover from the roadway west to the steel stake 1/6/2005 2:47:17 PM
|
INSP-Sprinkler Rough-in | 1/5/2005 | 1/5/2005 | 1/5/2005 | P | PART |
Troy Cobbley
|
|
|
The remaining underground supply piping to the tie in at the street is ok to cover. The underground supply piping from the roadway the the stub out still needs inspection 1/5/2005 2:54:04 PM
|
INSP-Sprinkler Rough-in | 1/3/2005 | 1/4/2005 | 1/4/2005 | A | PART |
Troy Cobbley
|
|
|
An additional 180' of supply piping running east is ok to cover 1/4/2005 10:46:09 AM
|
INSP-Sprinkler Rough-in | 1/3/2005 | 1/3/2005 | 1/3/2005 | P | PART |
Troy Cobbley
|
|
|
Underground supply piping is ok to cover for an additional 160' east of the roadway previously approved for cover 1/3/2005 4:00:03 PM
|
INSP-Sprinkler Rough-in | 12/29/2004 | 12/29/2004 | 12/29/2004 | P | PART |
Troy Cobbley
|
|
|
Ok to cover underground supply piping that is located under the roadway only. Per Terry the installer there will be two additional 45 degree elbows in the underground. Resubmitt plans showing these additional valves or provide verification Bill won't require resubmittals. 12/29/2004 1:31:57 PM
|
INSP-Sprinkler Rough-in/Hydro | 10/26/2004 | 10/26/2004 | 10/26/2004 | P | PART |
Troy Cobbley
|
|
|
Underground stubout only is ok to cover 10/26/2004 11:45:12 AM
|
Issue permit | | | 10/25/2004 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 10/11/2004 | | 10/21/2004 | | DONE |
|
|
|
|
Sprinkler Plan Check | 10/11/2004 | | 10/21/2004 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/21/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/21/2004 | | |
|
|
|
|
Inspection Record Card- Fire | 10/21/2004 | | 10/21/2004 | | DONE |
|
|
|
|
Telephone call | | | 10/21/2004 | | DONE |
|
|
|
Spoke with Alisha and told her that permit is ready & fees///10/21/04 4:55pm BAS
|
Application received | | | 10/11/2004 | | |
|
|
|
|