INSP-Final Inspection | 8/12/2010 | 8/18/2010 | 8/20/2010 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Conference | 7/27/2010 | 8/4/2010 | 8/11/2010 | A | DONE |
Troy Cobbley
|
|
|
Follow up conference with Keith (head of maintenance), on site, for project status and he stated that ADT would be contacting me.
|
INSP-Conference | 7/27/2010 | 7/27/2010 | 7/27/2010 | P | DONE |
Troy Cobbley
|
|
|
I spoke to the on site maintenance director named Keith about getting this permit finished. He was going to contact the fire alarm vendor. I set up a follow up inspection for next week.
|
INSP-Conference | 7/7/2010 | 7/7/2010 | 7/7/2010 | P | DONE |
Troy Cobbley
|
|
|
I went over the outstanding issues as per the permit history with Keith at ADT.
|
FIR-Aging Inspection | 3/17/2010 | 3/17/2010 | 3/24/2010 | | NR |
Troy Cobbley
|
|
|
Permit information forwarded to Stephanie and to Scott for further action.
|
Issue and Print Permit | | | 5/12/2005 | | DONE |
|
|
|
|
Alarm Plan Check | | | 5/9/2005 | | PASS |
|
|
|
Plan Modification. Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/9/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/9/2005 | | 5/9/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/9/2005 | | DONE |
|
|
|
|
Telephone call | | | 5/9/2005 | | DONE |
|
|
|
lft vm with dave whiting that permit and fees are ready to be picked up
|
Plan resubmittals received | | | 4/28/2005 | | |
|
|
|
|
INSP-Final Inspection | 4/12/2005 | 4/13/2005 | 4/13/2005 | A | FAIL |
Troy Cobbley
|
|
|
Two a/v's are mounted too high. Provide additional a/v's in the restrooms, as marked on plans,and any other common areas. Test smoke detector at the panel. Provide verification of note #14.
|
INSP-Final Inspection | 4/7/2005 | 4/8/2005 | 4/8/2005 | P | FAIL |
Troy Cobbley
|
|
|
Resubmitted plans still do not match sizing or routing as installed. Fix it or resubmit it. Riser on plans shows steel. As installed its half steel and half plastic. Water meter is wrong size. Reinspection fees are being applied.
|
FIR-Aging Inspection | 3/29/2005 | 3/29/2005 | 3/29/2005 | | NR |
Troy Cobbley
|
|
|
work in progress 3/29/2005 11:17:26 AM
|
Issue and Print Permit | | | 12/21/2004 | | DONE |
|
|
|
|
Plan assigned to (Mary) | 10/14/2004 | | 12/17/2004 | | DONE |
|
|
|
|
Alarm Plan Check | | | 12/17/2004 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/17/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/17/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/17/2004 | | 12/17/2004 | | DONE |
|
|
|
|
Telephone call | | | 12/17/2004 | | DONE |
|
|
|
Spoke with Dave and told him that permit is ready & fees///12/17/04 10:15am BAS
|
Plan resubmittals received | | | 12/14/2004 | | |
|
|
|
|
Meeting | | | 10/26/2004 | | DONE |
|
|
|
Meeting to discuss the ramifications with the FACP upgrade. The entire fire alarm system must be up upgraded to meet code.
|
Alarm Plan Check | | | 10/26/2004 | | FAIL |
|
|
|
Resubmittal required. No comments were written.
|
Application received | | | 10/14/2004 | | |
|
|
|
|