INSP-Final Inspection | 9/21/2005 | 9/22/2005 | 9/22/2005 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 9/16/2005 | 9/21/2005 | 9/21/2005 | P | FAIL |
Troy Cobbley
|
|
|
Provide signage on riser room door.
|
INSP-Final Inspection | 9/16/2005 | 9/16/2005 | 9/16/2005 | P | FAIL |
Troy Cobbley
|
|
|
Need signage on riser door, need test papers, signs on aux drains, certify backflow preventor, forward flush backflow preventor, provide head wrench.
|
INSP-Sprinkler Rough-in/Hydro | 8/10/2005 | 8/10/2005 | 8/10/2005 | P | PART |
Troy Cobbley
|
|
|
Hydro test for the wet system and anti-freeze loop passed. Contractor needs to provide test papers.
|
INSP-Sprinkler Rough-in/Hydro | 8/8/2005 | 8/9/2005 | 8/9/2005 | P | FAIL |
Troy Cobbley
|
|
|
Contact: Chris Lamb - Hydro Test Wet And Anti Freeze system; Phone #: ###-#### Hydro test of the anti-freeze loop failed and the overhead wet system would have passed if the piping from the check valve to the FDC had been included. Need to retest system
|
INSP-Supply line flush | 5/11/2005 | 5/11/2005 | 5/11/2005 | P | PASS |
Troy Cobbley
|
|
|
Inspection was for an underground hydro which passed
|
INSP-Supply line flush | 5/5/2005 | 5/10/2005 | 5/10/2005 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed.
|
INSP-Sprinkler Rough-in | 3/28/2005 | 3/29/2005 | 3/29/2005 | A | PART |
Troy Cobbley
|
|
|
Ok to cover dificient areas as noted on approved plans 3/29/2005 12:29:55 PM
|
INSP-Sprinkler Rough-in | 3/24/2005 | 3/25/2005 | 3/25/2005 | A | PART |
Troy Cobbley
|
|
|
See city approved plans for rooms that piping can be covered and for locations of deficiencies at these same rooms 3/25/2005 10:45:07 AM
|
INSP-Sprinkler Rough-in | 1/20/2005 | 1/21/2005 | 1/21/2005 | P | PART |
Troy Cobbley
|
|
|
Underground supply piping is ok to cover 1/21/2005 3:25:47 PM
|
Inspection Record Card- Fire | 12/1/2004 | | 12/1/2004 | | DONE |
|
|
|
|
Telephone call | | | 12/1/2004 | | DONE |
|
|
|
lft ms with recptionist ###-#### - permit is ready and no fee
|
Sprinkler Plan Check | 11/19/2004 | | 11/30/2004 | | PASS |
Bill Alexander
|
|
|
|
Plan resubmittals received | | | 11/19/2004 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 10/20/2004 | | 11/3/2004 | | DONE |
|
|
|
|
Sprinkler Plan Check | 10/20/2004 | | 11/3/2004 | | PART |
Bill Alexander
|
|
|
1.Provide corrected plans for Area #3, Plan FP-2, of which the line pipe sizes are impossible to read.
2. Area #2, 3 and 4 are obstructed (in the most demanding/remote areas). All obstructed areas shall be identified on the plans. Provide a minimum 8.5 x 11's with the areas identified addressing the type of obstructed construction relating to each (if different).
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/3/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/3/2004 | | 11/3/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/3/2004 | | DONE |
|
|
|
|
Telephone call | | | 11/3/2004 | | DONE |
|
|
|
lft vm regarding fee and permit is ready to be picked up
|
Issue and Print Permit | | | 11/3/2004 | | DONE |
|
|
|
|
Application received | | | 10/20/2004 | | |
|
|
|
|