INSP-Final Inspection | 11/15/2004 | 11/16/2004 | 11/16/2004 | A | PASS |
Troy Cobbley
|
|
|
Fire sprinklers finaled 11/16/2004 10:09:43 AM
|
DOC - Permit Finaled | 11/16/2004 | 11/16/2004 | 11/16/2004 | A | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 11/16/2004 10:09:47 AM
|
INSP-Final Inspection | 11/12/2004 | 11/15/2004 | 11/15/2004 | A | FAIL |
Troy Cobbley
|
|
|
Contractor did not have the letter from the structural engineer and alarms are not ready to go. 11/15/2004 1:16:12 PM
|
INSP-Sprinkler Rough-in/Hydro | 11/10/2004 | 11/12/2004 | 11/12/2004 | A | FAIL |
Troy Cobbley
|
|
|
Provide letter stating hangers are ok on bottom truss or relocate hanger to top of truss per approved drawings. Test interconnection to fire alarm system. Above ground and underground hydro test passed. Flush and forward flush passed. 11/12/2004 12:51:46 PM
|
Issue and Print Permit | | | 11/10/2004 | | DONE |
|
|
|
|
Sprinkler Plan Check | 11/9/2004 | | 11/9/2004 | | PASS |
Troy Cobbley
|
|
|
Plans approved with comments
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/9/2004 | | DONE |
Troy Cobbley
|
|
|
|
Inspection Record Card- Fire | 11/9/2004 | | 11/9/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/9/2004 | | DONE |
|
|
|
|
Telephone call | | | 11/9/2004 | | DONE |
|
|
|
called and talked to Wayne that his permit and fees are ready to be picked up
|
Miscellaneous action | | | 11/8/2004 | | DONE |
Troy Cobbley
|
|
|
On 11/3/04 I found that the tenant improvement portion of the fire sprinkler work had been complete. The superintendant for the general contractor confirmed that the tenant improvement plans had not been approved yet. I notified Bill Alexander for a double fee.
|
Application received | | | 10/28/2004 | | |
|
|
|
|
Plan assigned to (Bill) | 10/28/2004 | | | | |
|
|
|
|