Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberFIR04-00737
StatusFinaled
Name DE BEST FIRE PROTECTION
Site Address 925 N CLOVERDALE RD
Project NameSPR OH ADVENT SCH. GYM & CLASS
Customer Number 
ePlanReview 
Description
BOISE VALLEY ADVENTIST SCHOOL-ADDITION * To install complete fire sprinkler protection with the construction of a new 17,175-ft/2 single story, Type V-B, gymnasium & class addition. This work will include a wet and dry system riser with connections for the future protection of the entire school/facility. The addition is considered a separate building and will have a 2 hour fire wall separating it from the existing Type V-1 hr. building. Underground fire service supply was permitted under FIR04-00627. Fire sprinklers are used for area in the addition. Existing building requires fire sprinkler to satisfy IFC fire flow requirements (separate permit). The fire sprinkler system work shall comply with the IFC 2000, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD04-00709.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/2/20059/2/20059/2/2005PPASS
DetailsForrest France
Defficient items have been corrected and inspected, permit finaled.
INSP-Sprinkler Rough-in/Hydro8/29/20058/29/20058/29/2005PPART
DetailsForrest France
Re-hydrostatic test of the dry system passed inspection.
INSP-Final Inspection8/26/20058/26/20058/26/2005PFAIL
DetailsForrest France
Exposed CPVC line in attic space needs tenting, one branch line has the deflectors oriented opposite the roof pitch, provide approved lateral restraint for all sprig-ups over 4' in length, perform a hydrostatic test due to the number of changes and additional heads installed for the correction of spacing issues in the attic.
INSP-Sprinkler Rough-in/Hydro8/18/20058/18/20058/18/2005PCANC
DetailsTroy Cobbley
Wrong permit called in. See FIR 05-00124
INSP-Sprinkler Rough-in8/16/20058/16/20058/16/2005PFAIL
DetailsTroy Cobbley
Dry system tripped ok but became plugged with something
INSP-Sprinkler Rough-in/Hydro8/11/20058/11/20058/11/2005PPASS
DetailsTroy Cobbley
Wet system hydro test passed
INSP-Sprinkler Rough-in/Hydro8/10/20058/10/20058/10/2005PFAIL
DetailsTroy Cobbley
Wet system hydro test failed again.
INSP-Sprinkler Rough-in8/9/20058/10/20058/10/2005AFAIL
DetailsTroy Cobbley
Dave found leak in system. Test rescheduled for this afternoon.
INSP-Sprinkler Rough-in/Hydro7/28/20057/29/20057/29/2005PPASS
DetailsTroy Cobbley
contact dave. finish 24 hr air; air test passed
INSP-Sprinkler Rough-in/Hydro7/27/20057/28/20057/28/2005PPART
DetailsTroy Cobbley
contact dave. 24 hr air test.; Starting pressure at just above 42psi at 12:00
INSP-Sprinkler Rough-in/Hydro7/27/20057/28/20057/28/2005APASS
DetailsTroy Cobbley
Above ground hydro test passed.
INSP-Sprinkler Rough-in/Hydro7/27/20057/27/20057/27/2005PCANC
DetailsTroy Cobbley
Wrong permit called in. See FIR05-00124
INSP-Sprinkler Rough-in7/21/20057/25/20057/25/2005ACANC
DetailsTroy Cobbley
Canceled per Dave until resubmittals for piping changes are approved.
INSP-Sprinkler Rough-in7/20/20057/22/20057/22/2005PCANC
DetailsTroy Cobbley
Contact Dave Around 1 PM please.; Phone #: ###-#### Cancelled per Dave's request.
INSP-Sprinkler Rough-in5/6/20055/6/20055/6/2005PPART
DetailsTroy Cobbley
Sprinkler piping under mezzanine, including the ramp are ok to cover. Flexible cplg has been installed on rise up.
INSP-Sprinkler Rough-in5/4/20055/5/20055/4/2005AFAIL
DetailsTroy Cobbley
Inspection was for the area under the mezzanine as shown on the resubmitted plans. Plans do not show the upright heads for the combustible concealed space. There are six uprights mounted above the pendants. They are 200 degree QR brass uprights.
Plan resubmittals received  5/4/2005 DONE
Issue permit  5/2/2005 DONE
Sprinkler Plan Check4/25/2005 4/29/2005 PASS
DetailsBill Alexander
Major Field Modification
Plan assigned to (Bill)4/25/2005 4/29/2005 DONE
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  4/29/2005 DONE
Permit Ready to Issue  4/29/2005 DONE
Telephone call  4/29/2005 DONE
called left message permit is ready and fees 4/29/05 10:24am LEM
Inspection Record Card- Fire4/29/2005 4/29/2005 DONE
Plan resubmittals received  4/25/2005  
INSP-Sprinkler Rough-in/Hydro4/19/20054/20/20054/20/2005PFAIL
DetailsForrest France
Head required in entry north side for combustible concealled space. Move 4-way brace closer to change of direction on 3'' main. Flexible coupling req. on 2.5" main through floor at mech. mezz. Verify 10' length on lateral EQ bracing is sufficient. Two
INSP-Supply line flush4/4/20054/5/20054/5/2005APASS
DetailsTroy Cobbley
Undergroiund supply line flush passed
INSP-Sprinkler Rough-in3/23/20053/24/20053/24/2005APART
DetailsTroy Cobbley
terry; Phone #: ###-#### Dry system east side project ok to cover. 3/24/2005 9:27:17 AM
INSP-Sprinkler Rough-in/Hydro3/24/20053/24/20053/24/2005ACANC
DetailsTroy Cobbley
Contact: Terry - Cover Inspection; Phone #: ###-#### Duplicate inspection. 3/24/2005 9:31:26 AM
INSP-Sprinkler Rough-in3/22/20053/23/20053/23/2005AFAIL
DetailsTroy Cobbley
Contact: Terry - Cover Inspection; Phone #: ###-#### See field remarks on approved plans re EQ attatchments and ssu spacing. 3/23/2005 12:01:15 PM
CHANGE STATUS TO (ISS)  3/14/2005 DONE
(F) Reprint permit  2/3/2005  
Sprinkler Plan Check12/20/2004 12/29/2004 PASS
DetailsBill Alexander
Miscellaneous action  12/29/2004 DONE
Took revised resubmittal plans to Permit Test for calling and returning.
Telephone call  12/29/2004 DONE
lft vm with randy bowron ###-#### that permit is ready and no fee
Permit Ready to Issue  12/29/2004 DONE
Plan resubmittals received  12/20/2004  
Issue and Print Permit  12/9/2004 DONE
Permit Ready to Issue  12/8/2004 DONE
Inspection Record Card- Fire12/8/2004 12/8/2004 DONE
Telephone call  12/8/2004 DONE
Left message with Alishia that permit is ready & fees///12/08/04 2:30pm BAS
Plan assigned to (Bill)11/29/2004 12/7/2004 DONE
Sprinkler Plan Check11/29/2004 12/7/2004 PART
DetailsBill Alexander
1. Designer shall provide corrected calculations for the wet gymnasium meeting requirements of 14.4.4.1.1, 14.4.4.2 and 14.4.3.1.1.
PLANS/APPL TAKEN TO FRONT DESK  12/7/2004 DONE
Application received  11/29/2004