INSP-Final Inspection | 6/8/2005 | 6/8/2005 | 6/8/2005 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Supply line flush | 4/18/2005 | 4/19/2005 | 4/19/2005 | P | PASS |
Forrest France
|
|
|
Underground fire supply line flush OK.
|
INSP-Supply line flush | 3/11/2005 | 3/14/2005 | 3/14/2005 | A | PART |
Troy Cobbley
|
|
|
Underground hydro test passed. Rough-in failed. Trapeze hangers for the 6" main are overspace. Plans call for 10' max. Provide calcs and spacing requirements for the uni-strut tapeze on the 4" main. Provide verification for head temps at the unit heaters. Backflow preventer in wrong type of manufacturer. Head spacing and pipe size ok. Riser not looked at. 3/14/2005 11:33:22 AM
|
INSP-Sprinkler Rough-in/Hydro | 1/31/2005 | 2/1/2005 | 2/1/2005 | A | PART |
Rick Jackson
|
|
|
Please call one hour prior to arrival. Stan is the contact at ###-####. Thank you; Phone #: ###-#### Internet Inspection Request from: Trent Bice UG cover okay per resubmittals; 8 inch with tracer wire 2/1/2005 12:11:17 PM
|
Sprinkler Plan Check | 12/10/2004 | | 12/17/2004 | | PASS |
Bill Alexander
|
|
|
6" underground changed to 8" throughout.
|
Miscellaneous action | | | 12/17/2004 | | DONE |
|
|
|
Took approved revised plans to permit desk.
|
Telephone call | | | 12/17/2004 | | DONE |
|
|
|
left mess that permit is ready
|
Issue permit | | | 12/14/2004 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 12/3/2004 | | 12/10/2004 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/3/2004 | | 12/10/2004 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/10/2004 | | DONE |
|
|
|
|
Plan resubmittals received | | | 12/10/2004 | | |
|
|
|
|
Inspection Record Card- Fire | 12/10/2004 | | 12/10/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/10/2004 | | DONE |
|
|
|
|
Telephone call | | | 12/10/2004 | | DONE |
|
|
|
tlk to randy ###-#### the fee and permit is ready to be picked up
|
Application received | | | 12/3/2004 | | |
|
|
|
|