INSP-Final Inspection | 7/19/2005 | 7/21/2005 | 7/21/2005 | A | PASS |
Forrest France
|
|
|
Underground fire supply permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 7/5/2005 | 7/6/2005 | 7/6/2005 | A | PART |
Forrest France
|
|
|
Remote FDC piping hydrostatic test passed.
|
INSP-Sprinkler Rough-in/Hydro | 6/30/2005 | 7/5/2005 | 7/5/2005 | A | CANC |
Forrest France
|
|
|
Scheduled by a contractor via Hello! on 6/30/2005 at 3:31:19 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Jul 5 2005 7:17AM.
|
INSP-Sprinkler Rough-in/Hydro | 6/21/2005 | 6/23/2005 | 6/23/2005 | A | PART |
Forrest France
|
|
|
Underground fire supply hydrostatic test passed. Remote FDC underground pipe not tested at this time.
|
INSP-Supply line flush | 5/10/2005 | 5/13/2005 | 5/13/2005 | A | PART |
Forrest France
|
|
|
Underground fire supply line and remote FDC flush satisfactory. Still need hydrostatic test performed.
|
INSP-Sprinkler Rough-in | 3/25/2005 | 3/25/2005 | 3/25/2005 | P | PASS |
Troy Cobbley
|
|
|
george richardson ###-#### Underground fire supply and fdc connection ok to cover, verify gravel install below ball drip. 3/25/2005 1:13:04 PM
|
Inspection Record Card- Fire | 3/25/2005 | | 3/25/2005 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/25/2005 | | |
|
|
|
|
Sprinkler Plan Check | 2/25/2005 | | 3/3/2005 | | PASS |
Bill Alexander
|
|
|
PHASE 2
|
Plan assigned to (Bill) | 2/25/2005 | | 3/3/2005 | | DONE |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/3/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/3/2005 | | DONE |
|
|
|
|
Telephone call | | | 3/3/2005 | | DONE |
|
|
|
tlk to steven johson - ###-#### - at first when I said the 3rd reading he misunder me and thought is was fir05 permit not fir04 permit that is just me just 1st fee but i did cleared up (I hope)-that permit and fees are ready to be picked up
|
Plan resubmittals received | | | 2/25/2005 | | |
Bill Alexander
|
|
|
PHASE 2
|
INSP-Sprinkler Rough-in | 12/27/2004 | 12/28/2004 | 12/28/2004 | A | PART |
Rick Jackson
|
|
|
11 am for UG cover Phase I is completed to first 45 outside the building; rods used for the entire length 12/28/2004 12:16:40 PM
|
INSP-Sprinkler Rough-in | 12/23/2004 | 12/27/2004 | 12/27/2004 | P | PART |
Rick Jackson
|
|
|
steve; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles UG is okay to cover for base of riser; will complete full cover to first 45 on 12/28 12/27/2004 3:39:39 PM
|
Issue and Print Permit | | | 12/21/2004 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 12/3/2004 | | 12/20/2004 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/14/2004 | | 12/20/2004 | | PASS |
Bill Alexander
|
|
|
Plans delayed due to poor layout and useless information provided
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/20/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/20/2004 | | 12/20/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/20/2004 | | DONE |
|
|
|
|
Telephone call | | | 12/20/2004 | | DONE |
|
|
|
tlk to secretary ###-#### that permit and fees are ready to be picked up
|
Plan resubmittals received | | | 12/13/2004 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/3/2004 | | 12/10/2004 | | FAIL |
Bill Alexander
|
|
|
Please provide the following minimum information:
1. Provide a building permit to associate this permit with.
2. Provide a vicinity map of the facility involved with correct compass point.
3. Provide a site plan with the location of where this work will be involved with street names and correct compass point.
4. Provide a building floor plan with identifiable columns that represent and correlate with sheet #2 submitted.
5. Replace the (exposed) C-900 extending up through the floor with an approved piping material (and re-identify) since the IPC and/or the UPC will not allow this pipe and it's use to be exposed.
6. Standard "Eye Rod" bolts, if attached at the lower M.J. ell, will pull up under testing pressure and thus give and stretch the riser. Rotate them similar to the top connections for a correct installation practice.
|
Telephone call | | | 12/10/2004 | | DONE |
|
|
|
Faxed letter requesting basic information and requirements. (Attached in documents).
|
Application received | | | 12/3/2004 | | |
|
|
|
|