INSP-Final Inspection | 5/20/2005 | 5/20/2005 | 5/20/2005 | P | PASS |
Troy Cobbley
|
|
|
Fire sprinkler finaled
|
INSP-Final Inspection | 5/19/2005 | 5/19/2005 | 5/19/2005 | P | FAIL |
Troy Cobbley
|
|
|
Provide guage on supply side, provide ball drip for FDC, provide backflow certification and forward flush, provide pendants for the head box and provide wall PIV per the approved plans.
|
INSP-Sprinkler Rough-in/Hydro | 5/12/2005 | 5/13/2005 | 5/13/2005 | A | PART |
Troy Cobbley
|
|
|
Underground and overhead hydro test passed. Underground flush passed. See approved plans for overhead piping deficiencies.
|
INSP-Sprinkler Rough-in | 2/16/2005 | 2/17/2005 | 2/17/2005 | A | PART |
Troy Cobbley
|
|
|
Sprinkler piping over hardlid areas is ok to cover. Trapeze needs to be upsized per review notes. Underground supply piping is ok to cover. 2/17/2005 1:44:58 PM
|
Issue and Print Permit | | | 1/6/2005 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 12/10/2004 | | 1/5/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/30/2005 | | 1/5/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/5/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/5/2005 | | 1/5/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/5/2005 | | DONE |
|
|
|
|
Telephone call | | | 1/5/2005 | | |
|
|
|
tlk to john warnick - ###-#### that his permit and fee
|
Plan resubmittals received | | | 12/30/2004 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/10/2004 | | 12/17/2004 | | FAIL |
Bill Alexander
|
|
|
The data has been moved to a Word document attached to this case.
|
Miscellaneous action | | | 12/17/2004 | | DONE |
|
|
|
Returned plans to permit desk.
|
Telephone call | | | 12/17/2004 | | DONE |
|
|
|
Left message with answering service for John that plans failed and need picked up///12/17/04 10:25am BAS
|
Application received | | | 12/10/2004 | | |
|
|
|
|