Case Summary | | | 8/3/2005 | | DONE |
|
|
|
|
INSP-Final Inspection | 2/9/2005 | 2/9/2005 | 2/9/2005 | A | PASS |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 2/9/2005 at 7:09:13 AM. Contact: ###-####.
|
DOC - Permit Finaled | 2/9/2005 | 2/9/2005 | 2/9/2005 | A | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 2/9/2005 10:01:31 AM
|
INSP-Final Inspection | 2/4/2005 | 2/7/2005 | 2/7/2005 | A | FAIL |
Troy Cobbley
|
|
|
Could not give final due to ceiling tile not being installed. Sprinkler piping is ok to cover. 2/7/2005 8:31:01 AM
|
Plan resubmittals received | | | 1/14/2005 | | DONE |
|
|
|
Resubmittal for construction-Named (Phase 2).
|
Sprinkler Plan Check | 1/13/2005 | | 1/14/2005 | | PASS |
Bill Alexander
|
|
|
|
Plan assigned to (Bill) | 1/13/2005 | | 1/14/2005 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/14/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/14/2005 | | 1/14/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/14/2005 | | DONE |
|
|
|
|
Telephone call | | | 1/14/2005 | | DONE |
|
|
|
emailed paul that his permit and fees are ready to be picked up
|
Issue and Print Permit | | | 1/14/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/13/2005 | | 1/13/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/13/2005 | | |
|
|
|
|
Telephone call | | | 1/13/2005 | | DONE |
|
|
|
email pdmarcolina that their permit and fees are ready to be picked up
|
Plan resubmittals received | | | 1/13/2005 | | DONE |
|
|
|
Demolition Named (Phase 1)
|
Issue and Print Permit | | | 1/13/2005 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 12/30/2004 | | 1/12/2005 | | DONE |
|
|
|
|
Plan resubmittals received | | | 1/12/2005 | | DONE |
|
|
|
Using for review of demolition work only.
|
Sprinkler Plan Check | 1/12/2005 | | 1/12/2005 | | PART |
Bill Alexander
|
|
|
Phase 1 - Approved for demolition work only
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/12/2005 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 1/11/2005 | | 1/11/2005 | | DONE |
|
|
|
pciked up 1/10/05/mls
|
Telephone call | | | 1/5/2005 | | DONE |
|
|
|
e mail Paul M that permit have failed to be picked up
|
Sprinkler Plan Check | 12/31/2005 | | 1/4/2005 | | FAIL |
Bill Alexander
|
|
|
1. Plan submittal denied due to required IBC and IFC review information of which this permit is associated with. Resubmit upon final IFC building approval. Much information is cleaned from the building and building fire reviews which includes complete permit scope of work, (verifying fire sprinkler work is covered), building construction type, (combustible cavities, etc.), total area of work (verifying with total area with what was submitted), Occupancy use, (addressed for fire sprinkler hazards), construction issues for possible trade off for fire sprinkler requirements (water curtain - separation, etc), detailed construction information associated in the permit (which would verify questions addressed in item #2 and 4 below), and more. (BMC 7-01-50:901.2, IFC 105.4.2)
2. Plan information is confusing. Per the Designer, the "General Notes" indicates all solid lines indicate new walls? If this is the case the plan submittal is incomplete and shall include all locations associated with the fire sprinkler layout affected or not affected (to be determined by the AHJ), with the associated building permit (reference the following general detail). (BMC 7-01-50:901.2, IFC 105.4.2)
3. Provide information regarding the hanger attachments (which must be listed), for each armover requiring support and include the type of connection making to the structure. This will require some associated structural information above the ceiling. (BMC 7-01-50:901.2, IFC 105.4.2, NFPA 13:14.1.3[22])
4. Include all associated ceiling height elevation/s. (BMC 7-01-50:901.2, IFC 105.4.2, NFPA 13:14.1.3[37])
|
Application received | | | 12/30/2004 | | |
|
|
|
|