Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberFIR04-00812
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 917 S LUSK ST
Project NameSPR UG KEYNETICS
Customer Number 
ePlanReview 
Description
KEYNETICS OFFICE (SHELL & CORE) - To install a 6" fire service supply into the south corner of a new 27,958-ft/2 three story, structure. This work will be accomplished in stages. The first is stub out under the footing and the second to an approved water source. A separate plan/s and permit will be required for the overhead fire sprinkler system. The fire sprinkler underground work shall comply with NFPA 13-2002, NFPA 24-2002 the IFC-2000, attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum fire code. This permit is attached to building permit: BLD04-02409.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/15/200512/15/200512/15/2005PPASS
DetailsForrest France
Underground fire supply line finaled.
INSP-Sprinkler Rough-in/Hydro12/9/200512/12/200512/12/2005ADEFR
DetailsForrest France
mike Note: 24 hr air test; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles NOTE: Wrong permit number called in, this was meant for FIR05-00385 for the overhead, not under FIR04-00812 for the associated UG supply.
INSP-Sprinkler Rough-in11/3/200511/4/200511/4/2005PPART
DetailsForrest France
2nd floor corridor hard lid and 1st floor restrooms hard lid are okay to cover for overhead rough-in.
INSP-Supply line flush8/9/20058/9/20058/9/2005APART
DetailsForrest France
Two hour hydrostatic test and supply line flush both passed inspection.
INSP-Supply line flush7/27/20057/27/20057/27/2005AFAIL
DetailsForrest France
Underground fire supply work appears to be installed in a satisfactory manner, however the resubmitted plans and notes with scope of work does not address phase 2 (connection to city supply) work. This work must be submitted and approved prior to field inspection and sign off.
Plan resubmittals received  7/26/2005 DONE
INSP-Supply line flush1/18/20051/19/20051/19/2005APART
DetailsRick Jackson
Mike; Phone #: ###-#### Internet Inspection Request from: Jan Rice UG stub out only - okay; used one piece riser 1/19/2005 10:10:01 AM
Issue permit  1/10/2005 DONE
Plan assigned to (Bill)12/30/2004 1/7/2005 DONE
Sprinkler Plan Check1/7/2005 1/7/2005 PASS
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  1/7/2005 DONE
Inspection Record Card- Fire1/7/2005 1/7/2005 DONE
Permit Ready to Issue  1/7/2005 DONE
Plan resubmittals received  1/6/2005 DONE
Telephone call  1/5/2005 DONE
Spoke with Jeff and told him that plans failed and need picked up////1/5/04 8:00am BAS
Sprinkler Plan Check12/30/2004 1/4/2005 FAIL
DetailsBill Alexander
1. Underground tap is unacceptable with Boise City Fire Department and agreements with United Water, (unless verification from United Water is provided that the hydrant tapped main will be extended through the parking lot to another supply connection or extend and loop back to the street main). Provide a separate tap off the street main and extend it into the building for the fire sprinkler supply. (BMC 7-01-46:IFC 508.6)
Application received  12/30/2004