INSP-Final Inspection | 3/10/2005 | 3/10/2005 | 3/10/2005 | A | PASS |
Troy Cobbley
|
|
|
fire sprinkler finaled
|
DOC - Permit Finaled | 3/10/2005 | 3/10/2005 | 3/10/2005 | A | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 3/10/2005 11:25:45 AM
|
Sprinkler Plan Check | 2/18/2005 | | 2/22/2005 | | PASS |
Bill Alexander
|
|
|
|
Miscellaneous action | | | 2/22/2005 | | DONE |
|
|
|
Emailed approved documents to Rick Reynnolds.
|
INSP-Final Inspection | 2/18/2005 | 2/18/2005 | 2/18/2005 | A | PART |
Troy Cobbley
|
|
|
Temporary occupancy. Viking still needs to finish three sprinkler pendants
|
INSP-Sprinkler Rough-in/Hydro | 2/9/2005 | 2/9/2005 | 2/9/2005 | P | PART |
Troy Cobbley
|
|
|
Hydro test for the west system passed. Still need annual certification for the anti-freeze system. 2/9/2005 3:42:10 PM
|
INSP-Final Inspection | 2/1/2005 | 2/2/2005 | 2/2/2005 | A | FAIL |
Rick Jackson
|
|
|
ronny; Phone #: ###-#### Internet Inspection Request from: Barbara Moore East riser hydro okay; west riser has minor leak at vic at top of riser - will need to do hydro test over; sprinkler and anti=freeze loop overdue annual certification 2/2/2005 10:48:14 AM
|
Inspection Record Card- Fire | 1/25/2005 | | 1/25/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/25/2005 | | DONE |
|
|
|
|
Telephone call | | | 1/25/2005 | | DONE |
|
|
|
tlk to rick reynolds ###-#### that his permit and fees are ready to be picked up cmc
|
Issue permit | | | 1/25/2005 | | |
|
|
|
|
Plan assigned to (Bill) | 1/18/2005 | | 1/24/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/18/2005 | | 1/24/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/24/2005 | | DONE |
|
|
|
|
Application received | | | 1/18/2005 | | |
|
|
|
|