Permit Information
Permit NumberFIR05-00033
StatusFinaled
Name SIMPLEX/GRINNELL
Site Address 404 S 8TH ST (BASE / 1ST / 2ND FLRS)
Project Name8TH STREET MARKETPLACE
Customer Number 
ePlanReview 
Description
To replace an existing fire alarm system. The required manual fire alarm system includes sprinkler monitoring, elevator recall/shutdown, required automatic detection, HVAC shutdown, fire/smoke damper control, door release and notification throughout. The smoke control system as required per IFC 907.2.13 has not been implemented at this time. The required smoke detectors are to be installed and a general alarm shall be initiated on receipt of a single smoke detector. A voice/evac notification system is required per IFC 907.2.13.2.

The freight elevator located on the west side of the building is not for personnel and does not have recall controls. Nor do they plan on upgrading in the near future, so there are no fire alarm system components shown on the design that are associated with this elevator.

2/27/2006 - Plan Modification. A single cooking hood is indicated in the Café Ole suite B-120 (basement). The 75 cd S/S has been relocated to the east wall, creating insufficient visual coverage east of the walk-in cooler. Provide additional strobe coverage for this space.

The NAC circuits have changed, so the PDS Fire Inspector to compare and field verify all EOLs to the values on the riser.

The FACP and the NAC panels have been relocated, allowing the installer to delete four smoke detectors (used for panel protection). The new location is near the elevator, it appears that the elevator recall smoke detector will be utilized for the panel protection. See comment #11 for smoke detector coverage for the atrium.

The associated building permit (BLD 03-02412) is to remodel areas located in the basement and on the 1st and 2nd floors of a building located in "The 8th Street Market Place" and addressed as 404 S. 8th Street. Selective demolition is also covered under this permit. Work is to include new core restrooms in the basement and on the 2nd floor, a wheelchair lift, a new 8th Street entrance, new Broad Street entrances, exterior wall finishes for the North wall, new elevated concrete terrace, and an expanded roof structure all per the approved drawings and the plan review report on file. The location of fire sprinkler heads shall comply with NFPA 13-1999 as regulated by the Fire Department. DRH03-00064 (12-8-03) A COPY OF A LICENSE AGREEMENT WITH ACHD ALLOWING DOORS TO SWING INTO THE PUBLIC WAY SHALL BE SUBMITTED TO THE BUILDING DEPARTMENT BEFORE THIS PERMIT IS FINALED. **CJW** 8TH STREET MARKETPLACE - BUILDING 404 - BASEMENT/1ST/2ND FLOORS) (2-24-05) PLAN MODIFICATION TO DEMOLISH A 400 SQUARE FOOT 1 STORY WITH BASEMENT PORTION OF THIS BUILDING LOCATED NEXT TO THE ALLEY TO CREATE AN AREA FOR TRANSFORMERS TO SERVE THE NEW HOTEL BUILDING THAT WILL BE LOCATED ACCROSS THE ALLEY. This building is fire sprinklered to substitute for 1-hr fire-resistance rated construction.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary  7/30/2008  
Case Summary  3/3/2008 DONE
(F) Reprint permit  3/3/2008 DONE
INSP-Final Inspection12/20/200712/21/200712/21/2007APASS
DetailsForrest France
Fire alarm permit finaled. Remainder of required building upgrade work to be completed via separate tenant permits.
Miscellaneous action  12/7/2007 DONE
Attached this permit to Building Permit BLD03-02412 Project # PRJ05-06247 per Sam Rogers
INSP-Final Inspection11/26/200711/27/200711/27/2007APART
DetailsForrest France
Testing completed for notification devices at the basement, first and third floors, also completed initiating device testing including all smoke detectors, ansul kitchen system, waterflow, pull station. Final pending the installation of notification devices at floors, rooms and areas currently occupied but indicated on the plans as "unoccupied" and therefore are missing required coverage. See clouded red lines on approved set for locations at the basement, 1st, 2nd and 4th floors.
INSP-Conference11/26/200711/26/200711/26/2007PDONE
DetailsForrest France
Job scheduling.
INSP-Final Inspection11/19/200711/21/200711/21/2007APART
DetailsForrest France
Tested notification devices for the 1st thru 4th floors, no access provided for some areas on the 3rd and 1st floors-will need to retest, need to remove one existing SD at the 4th floor, noted on plans devices tested today including SD's and one pull station, fire doors at some locations are not adjusted correctly for full closure, need to test remainder of initiation devices and a/v's at next inspection.
Alarm Plan Check  10/11/2007 PASS
Fire Alarm Review 5th 2007 NFPA 72 Solid Joist Construction changes used.
Plan assigned to (Mike)10/8/2007 10/11/2007 PASS
10/11/2007 09:45:10 MWT - activity updated through activity FIRA22 from case FIR05-00033.
PLANS/APPL TAKEN TO FRONT DESK  10/11/2007  
Ready for Re-Issue
Inspection Record Card- Fire10/11/2007 10/11/2007 DONE
Telephone call  10/11/2007 DONE
left vm for charlie bayne at ###-#### - permit ready and fees given
Permit Ready to Issue  10/11/2007 DONE
(F) Reprint permit  10/11/2007 DONE
CHANGE STATUS TO (ISS)  10/11/2007  
Plan resubmittals received  10/8/2007  
received 1 application, 3 material lists 1 copy of sheet 1,2,3,4,5,6, of 11 and 2 copys of sheets 7,8,9,10,11 sent to fire
Telephone call  1/24/2007 DONE
telcon and email with Rich Lewis, Rolf Jensen Associates (###-####) regarding spacing requirements for smoke detectors in the corridor having open ceiling joists over 12" deep. I agreed to consider using the 2007 ed of NFPA 72 as an alternate design for this particular situation.
Telephone call  1/19/2007 DONE
Telcon from Rich Lewis, Rolf Jensen, Walnut Creek ###-####, to discuss smoke detector requirements for ceilings of open solid joists more than 12" deep. I referenced NFPA 72, 5.7.3.2.4 (B)(2). We agree that paragraph applied but he was looking for "a more reasonable approach". I indicated we must follow prescribed code or an approved alternate design stamped by a professional engineer adn that we are willing to consider such an engineered alternate design as prescribed by the IFC, using a second engineer of our choice to verify the proposed design, to be paid for by the owner. He indicated he would suggest that alternative to the general contractor who he was working for.
INSP-Final Inspection7/10/20067/10/20067/10/2006PPART
DetailsForrest France
C/N items from the previous inspection have been verified for completion, tested main FACP batteries, AC loss, phone lines, smoke above panel, need to provide locks at breakers, tested tamper switches, flow switches, addresses at flows do not match map or actual location. SD, manual pulls and notification to be tested at next inspection request. Duct detector testing is complete.
Override - Parcel Holds1/1/19001/1/19007/10/2006  
INSP-Final Inspection6/26/20066/29/20066/29/2006AFAIL
DetailsForrest France
Tested all duct detectors today, one detector(device 30) in the basement failed to function, one detector on the 2nd floor will need to be relocated as it is upstream of a return grill, need to change descriptor of one detector location at the cafe ole office area. Noted that the SD's located adjacent to the atrium in several locations will not function as installed due to open ceiling beam obstructions greater than 12" in depth.
Override - Parcel Holds1/1/19001/1/19006/26/2006  
Case Summary  6/23/2006  
FIR-Aging Inspection5/30/20065/30/20066/5/2006 DONE
DetailsForrest France
Work in progress.
Miscellaneous action  6/1/2006 DONE
Called Charlie to notify of the required 3 hour fire separation (no smoke requried) between the two buildings and inform him that the smoke detectors for the atruim coverage are mounted on open beam ceilings (6 areas) and believe the beams to be 12" or greater, which means improper smoke detector coverage.
Alarm Plan Check  2/28/2006 PASS
Plan Modification. See scope for modifications. Approved pending field inspection of fire alarm permit comments.
PLANS/APPL TAKEN TO FRONT DESK  2/28/2006 DONE
Telephone call  2/28/2006 DONE
lft vm with chris willis ###-#### that permit and fees are ready to be picked up
Inspection Record Card- Fire2/28/2006 2/28/2006 DONE
Issue and Print Permit  2/28/2006 DONE
Plan resubmittals received  2/15/2006  
Override - Parcel Holds  3/28/2005  
Issue permit  3/28/2005  
Plan assigned to (Mary)1/18/2005 3/18/2005 DONE
Alarm Plan Check  3/18/2005 PASS
Approved pending field inspection of fire alarm permit comments.
PLANS/APPL TAKEN TO FRONT DESK  3/18/2005 DONE
Inspection Record Card- Fire3/18/2005 3/18/2005 DONE
Permit Ready to Issue  3/18/2005 DONE
Plan resubmittals received  3/11/2005  
Alarm Plan Check  3/2/2005 FAIL
Resubmittal required. Faxed comments to Chris Willis (Simplex) and Jon Van Stone (E2).
Plan resubmittals received  2/14/2005 DONE
Case Summary  2/14/2005 DONE
Alarm Plan Check  2/7/2005 FAIL
No comments written, met with Jeff (E2 Co) to define deficiencies and the unoccupied spaces. Resubmittal required.
Application received  1/18/2005