INSP-Final Inspection | 1/27/2005 | 1/27/2005 | 1/27/2005 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 1/27/2005 at 10:36:32 AM. Contact: ###-####.
|
DOC - Permit Finaled | 1/27/2005 | 1/27/2005 | 1/27/2005 | P | PASS |
Rick Jackson
|
|
|
Finaled by inspector at 1/27/2005 4:33:07 PM
|
Plan resubmittals received | | | 1/27/2005 | | PASS |
Bill Alexander
|
|
|
Field verify code conformance
|
Miscellaneous action | | | 1/27/2005 | | DONE |
|
|
|
Electronically transmitted approval information to Brodie Stenquest and Troy Cobbley 3:15pm.
|
INSP-Final Inspection | 1/25/2005 | 1/25/2005 | 1/25/2005 | P | FAIL |
Troy Cobbley
|
|
|
Sprinkler work at the draftstop near at the south end of the store has not been done. Some deficiencies have been corrected that have not been shown on the plans. This includes four heads under a duct and a single upright under the old hood. Verify with Bill Alexander if resubmittal is required of just field verification. The tamper switch that is shown on the sprinkler plans has wire already run to the facp but no permit. 1/25/2005 3:10:26 PM
|
Issue and Print Permit | | | 1/25/2005 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 1/18/2005 | | 1/24/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/18/2005 | | 1/24/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/24/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/24/2005 | | 1/24/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/24/2005 | | DONE |
|
|
|
|
Telephone call | | | 1/24/2005 | | DONE |
|
|
|
lft mes with receptionist that permit and fees are ready to be picked up!
|
Application received | | | 1/18/2005 | | |
|
|
|
|