INSP-Final Inspection | 9/7/2005 | 9/8/2005 | 9/8/2005 | P | PASS |
Forrest France
|
|
|
Fire alarm permit finaled.
|
INSP-Final Inspection | 8/31/2005 | 9/1/2005 | 9/1/2005 | A | PART |
Forrest France
|
|
|
Provide permanent dual phone lines or approval letter for temporary lines at job trailer.
|
Miscellaneous action | | | 9/1/2005 | | DONE |
|
|
|
Received letter from Joe Jackson (ESI) that the construction trailer will remain and the phone lines will be intact. Qwest is to be out to the site 9/6 for permanent phone lines in the building. Sam Rogers has approved a temp occupancy based upon the letter and the phone install date. Existing phone lines have not been tested.
|
INSP-Final Inspection | 8/30/2005 | 8/31/2005 | 8/31/2005 | P | PART |
Forrest France
|
|
|
Forrest, Here is the inspection request for the completion of the final test at Trinity Presbyterian. If there is any problems meeting out there at 12:00p.m., please let us know. My cell is ###-#### if you cannot reach me at the office. Thanks, Jason; Phone #: ###-#### Internet Inspection Request from: Jason Minnick
Forrest, all checked out, one final issue is the phone lines are routed to the General Contractors trailer (temproary), so I did not test them. ESI is aware of the situation and will need to determine their plan of attack. I have told Jason and he will contact them. They have a choice of two options. 1) Provide the two permanent phone lines and test. 2) If they want to request a "temp" so they can move this weekend, they will need to supply a letter stating the trailer and phone lines will remain intact til the permanent ones are provided, probably need to test also. Sam is off tomorrow, so if they want a temp, they will need to request it today.
|
Case Summary | | | 8/31/2005 | | DONE |
|
|
|
|
INSP-Alarm Testing | 8/29/2005 | 8/30/2005 | 8/30/2005 | A | PART |
Forrest France
|
|
|
Partial inspection performed on area B, tested smoke and heat detectors, manual pull stations, and horn strobes, still need to test duct smoke detectors, battery, phone lines.
|
INSP-Final Inspection | 8/26/2005 | 8/29/2005 | 8/29/2005 | A | NR |
Forrest France
|
|
|
Inspection is scheduled for 8/30 at 12:00 noon.
|
INSP-Final Inspection | 8/25/2005 | 8/26/2005 | 8/26/2005 | A | FAIL |
Forrest France
|
|
|
The strobe lens on several notification devices throughout areas A and B are below the allowed height AFF for wall mounted applications.
|
INSP-Final Inspection | 8/24/2005 | 8/25/2005 | 8/25/2005 | P | CANC |
Forrest France
|
|
|
Inspection has been rescheduled for friday the 26th per Jason at ###-####.
|
Plan assigned to (Mary) | 1/21/2005 | | 7/6/2005 | | DONE |
|
|
|
|
Alarm Plan Check | | | 7/6/2005 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/6/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/6/2005 | | 7/6/2005 | | DONE |
|
|
|
|
Telephone call | | | 7/6/2005 | | DONE |
|
|
|
called told mike permit is ready and no fees
|
Permit Ready to Issue | | | 7/6/2005 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/6/2005 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/1/2005 | | |
|
|
|
|
Case Summary | | | 7/1/2005 | | DONE |
|
|
|
|
Alarm Plan Check | | | 1/25/2005 | | FAIL |
|
|
|
Resubmittal required. Faxed comments to Jason Minnick (AEI).
|
Application received | | | 1/21/2005 | | |
|
|
|
|