Permit Information
Permit NumberFIR05-00068
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 12400 W MCMILLAN RD
Project NameSPR OH CENTENIAL PERFORNING
Customer Number 
ePlanReview 
Description
CENTENNIAL HIGH SCHOOL PERFORMING ARTS CENTER * To install a complete overhead fire sprinkler system with Class III, 1½" and 2½" hose connections on the each side of the stage in a new 32,606-ft/2, one story, Type II-B theater/classroom building. The underground fire service supply was installed under separate fire permit FIR04-00619 (by the same contractor). Fire sprinklers are used for area. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD04-01188.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/18/20061/19/20061/19/2006APASS
DetailsTroy Cobbley
Sprinkler permit finaled
Telephone call  1/13/2006 DONE
Trent called on ceiling problem in Band Storage Room. Basically indicated that it will have to meet minimum code.
Plan resubmittals received  1/11/2006 PASS
DetailsBill Alexander
Standpipe hose valves resubmitted.
Miscellaneous action  1/11/2006 DONE
Faxed floor plan of Band Storage room ceiling problems.
INSP-Final Inspection12/28/200512/29/200512/29/2005PFAIL
DetailsTroy Cobbley
Need to do all of the riser inspection including the forward flush. Provide E.Q. on the three sprig ups. Provide the correct connections for the stage hose valves. There is a clearance issue in the storage room. Check ball drip.
INSP-Final Inspection10/19/200510/20/200510/20/2005PFAIL
DetailsTroy Cobbley
Project is not ready for final. Need the latest and greatest plans, canopies missing, taped heads...ect.
INSP-Sprinkler Rough-in/Hydro10/19/200510/20/200510/20/2005PPASS
DetailsTroy Cobbley
Above ground hydro test passed
INSP-Sprinkler Rough-in/Hydro7/21/20057/21/20057/21/2005PPART
DetailsTroy Cobbley
Hanger dificiencies as marked on the last edition of the approved have been corrected but the latest revision of the plans was not on site.
Inspection Record Card- Fire6/28/2005 6/28/2005 DONE
Issue and Print Permit  6/28/2005 DONE
Plan assigned to (Bill)6/24/2005 6/27/2005 DONE
Sprinkler Plan Check6/24/2005 6/27/2005 PASS
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  6/27/2005 DONE
Permit Ready to Issue  6/27/2005 DONE
Telephone call  6/27/2005 DONE
tlk to trent bice ###-#### that permit is ready to be picked up
Plan resubmittals received  6/24/2005 DONE
INSP-Sprinkler Rough-in5/19/20055/20/20055/20/2005APART
DetailsTroy Cobbley
Sprinkler piping fo rthe most part is ok. See city approved plans for locations of deficiecies which include missing hangers, modified routing of piping, deletion of heads and additional heads to be required under duct work in the auditorium. Plans will n
INSP-Sprinkler Rough-in5/3/20055/3/20055/3/2005PPART
DetailsTroy Cobbley
Sprinkler piping for room 137 is ok to cover. Looked at the eq bracing for the north half of building. It looks ok.
Issue and Print Permit  3/14/2005 DONE
Sprinkler Plan Check3/2/2005 3/11/2005 PASS
DetailsBill Alexander
Plan assigned to (Bill)3/2/2005 3/11/2005 DONE
PLANS/APPL TAKEN TO FRONT DESK  3/11/2005 DONE
Inspection Record Card- Fire3/11/2005 3/11/2005 DONE
Permit Ready to Issue  3/11/2005 DONE
Plan resubmittals received  3/2/2005 DONE
Case Summary  3/2/2005 DONE
Plan assigned to (Bill)2/3/2005 2/8/2005 DONE
Sprinkler Plan Check2/3/2005 2/8/2005 PART
DetailsBill Alexander
1. IFC 905.3.5 Stages. This stage qualifies for a Class III wet standpipe system with 1.5-inch and 2.5-inch hose connections on each side of the stage. The designer has located (undefined) standpipe hose connections on each side of the stage openings (curtain locations). Relocate connectiosn to side of each stage exit door. Revise plans and resubmit and include and/or verify the following:
a. Elevation view/s addressing the location/height of valves, etc., from the floor. (NFPA 14:8.1.5)
b. Manufacturer's data submittals addressing the valves installing, with correct caps. (NFPA 14:8.1.4)
c. This is a Wet, Manual and Combined System. I will contain pressurized water (insufficient for required pressures and flows) and is sharing a Fire Department Connection with the fire sprinkler system. This design cannot be accepted as provided and will require modifications:
i. Hydraulically designed standpipe systems shall be designed to provide the waterflow rate required by Section 7.10 at a minimum residual pressure of 100 psi at the outlet of the hydraulically most remote 2½" hose connection and 65-psi at the outlet of the hydraulically most remote 1½" hose station. NOTE: Any requirement for the installation of fire hose on standpipes shall be omitted. (BMC 7-01-59, IFC 905.1.1, NFPA 14:7.8.1.1)
ii. In addressing item "i" above, include a water supply that will be available in conjunction with the service supply, by a responding Fire Department pumper. Obtain from the Fire Marshall (Dave Miller-[208] ###-####) the available pump booster (water supply) available and design the standpipe system accordingly. A sign also be placed at the connection which indicates the pressure required at the inlets to deliver the system demand (reference item . (NFPA 14:7.10.1.2*, 6.3.5.2.2, 4.10)
iii. Provide a flow switch and corresponding test connection for the standpipe system. Include verbiage that the (standpipe) systems control, drain, and test connection valves signs shall address their purpose and identifying the system and area it controls. (NFPA 14:5.7*, 6.2.8.2)
iv. Provide earthquake bracing and include it on the plans. (NFPA 14:6.1.2.5)
v. Provide hanger location and address types which include any trapeze hangers and their engineering (along with the fire sprinkler system) meeting requirement of NFPA 14:6.4.2.1 and 6.4.2.2.

2. Plan modifications required. Plan FP4 of 5, Band Room #100. Water with correct densities is required to wet all walls and floor areas throughout this facility. Revise and resubmit. (IFC 104.3, 106, 107.2.2, 901.6)

3. Modifications required. Plan FP4 of 5, Choir Room #102. Water with correct densities is required to wet all walls and floor areas throughout this facility. Revise and resubmit. (IFC 104.3, 106, 107.2.2, 901.6)

4. Design area #4 Rest Rooms incorporates room design method and/or with a reduced ceiling height for the maximum reduction for 10'-0". The lobby has a higher ceiling and would appear to put a higher demand per line (more heads flowing). Verify and submit with separate calculations.

5. If installing a Riser Manifold®, Ready Riser® or similar, provide the manufacturers data submittals and identify the individual model installing. (NFPA 13:14.1.4, BMC 7-01-50-901.2, IFC 105.4)

6. Backflow prevention is not provided or addressing required forward flow components/provisions. Provide forward flow test piping and appurtenance, in accordance with NFPA 13:8.16.4.6.1*. (BMC 7-01-50-901.2, IFC 105.4)

7. Provide manufacturers data submittals for the intermediate level/rack storage type sprinklers or the "shield" installing to the Sprinklers, installed under open gratings. (BMC 7-01-50-901.2, IFC 105.4, NFPA 13:8.5.5.3.3)
PLANS/APPL TAKEN TO FRONT DESK  2/8/2005 DONE
Inspection Record Card- Fire2/8/2005 2/8/2005 DONE
Permit Ready to Issue  2/8/2005 DONE
Telephone call  2/8/2005 DONE
tlk to d weland ###-#### that permit and fees are ready to be picked up
Issue and Print Permit  2/8/2005 DONE
Application received  2/3/2005