INSP-Final Inspection | 4/20/2006 | 4/21/2006 | 4/21/2006 | A | PASS |
Forrest France
|
|
|
Final fire alarm inspection passed, permit finaled.
|
INSP-Final Inspection | 4/20/2006 | 4/20/2006 | 4/20/2006 | P | FAIL |
Forrest France
|
|
|
The outside bell failed to operate upon water flow, elevator lobby smokes tested okay, tampers at the basement and 1st floor tested okay.
|
INSP-Final Inspection | 4/18/2006 | 4/19/2006 | 4/20/2006 | P | DEFR |
Forrest France
|
|
|
Scheduled by a contractor via Hello! on 4/18/2006 at 3:35:00 PM. Contact: ###-####.
|
INSP-Final Inspection | 4/13/2006 | 4/14/2006 | 4/14/2006 | A | NR |
Forrest France
|
|
|
Project not ready for inspection due to related fire sprinkler issues and a non-functional elevator.
|
CHANGE STATUS TO (ISS) | | | 3/7/2006 | | DONE |
|
|
|
All Fire Alarm items in the Foster Building have NOT been tested. These items are a part of the shell/core for BODO #4.
|
INSP-Final Inspection | 2/27/2006 | 2/28/2006 | 2/28/2006 | A | PASS |
Forrest France
|
|
|
c/n items have been completed, fire alarm permit for BODO #4 has beeen completed.
|
INSP-Alarm Testing | 11/22/2005 | 11/23/2005 | 11/22/2005 | P | CANC |
Forrest France
|
|
|
Scheduled by a contractor via Hello! on 11/22/2005 at 2:37:38 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Nov 22 2005 2:39PM.
|
CHANGE STATUS TO (ISS) | | | 11/22/2005 | | DONE |
|
|
|
previously issued
|
Inspection Record Card- Fire | 11/21/2005 | | 11/21/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/21/2005 | | DONE |
|
|
|
|
Telephone call | | | 11/21/2005 | | DONE |
|
|
|
Called Kurt & left msg. permit ready to pick up on 11/21/05 @ 2:39 by CW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/18/2005 | | DONE |
|
|
|
|
Alarm Plan Check | | | 11/17/2005 | | PASS |
|
|
|
Plan Modification will be issued when additional required cutsheets have been received. (should be 11/18).
Approved pending field inspection of fire alarm permit comments.
|
Plan resubmittals received | | | 11/3/2005 | | |
|
|
|
|
INSP-Alarm Testing | 10/27/2005 | 10/28/2005 | 10/28/2005 | A | PART |
Forrest France
|
|
|
A temporary approval was signed with Sam Rogers permission pending resubmittals for changed EOL, west elevator completion, permanent signage at the FACP room door.
|
INSP-Sprinkler Rough-in | 10/27/2005 | 10/28/2005 | 10/28/2005 | A | CANC |
Forrest France
|
|
|
brian ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
INSP-Alarm Testing | 10/24/2005 | 10/25/2005 | 10/25/2005 | A | FAIL |
Forrest France
|
|
|
Provide audibility in the FACP room, provide signage at door to FACP room, provide resubmittals for EOL changes and added horn for FACP room, west elevator is not complete yet, provide Knox box with key and map, Foster bld. monitoring and elevator controls are incomplete.
|
INSP-Alarm Testing | 10/24/2005 | 10/24/2005 | 10/24/2005 | A | FAIL |
Forrest France
|
|
|
Need to retest elevator lobby smoke detectors as they have been connected and reconnected for ceiling tile installation, need to test elevator heat detector in pit, provide sign at FACP room, no knox box provided yet, need audibility in the FACP room as discussed.
|
INSP-Alarm Testing | 10/18/2005 | 10/21/2005 | 10/21/2005 | A | FAIL |
Forrest France
|
|
|
Heat detector in the north elevator pit is too far from the sprinkler head, provide resubmittals for the EOL 2nd floor, tape on strobe and no ceiling tile 1st floor north, west elevator is not complete, provide sign at the door to FACP room, provide audible notification for the electrical room and FACP, provide knox box.
|
INSP-Alarm Testing | 10/20/2005 | 10/20/2005 | 10/20/2005 | P | FAIL |
Forrest France
|
|
|
PIV tamper failed to function properly, the north elevator failed to recall upon smoke detection, the west elevator is not completed to allow testing, elevator control voltage needs to be monitored as a supervisory not a trouble signal, provide a sign at the door to the FACP, testing not completed today due to time constraints.
|
Issue permit | | | 10/20/2005 | | |
|
|
|
|
Alarm Plan Check | | | 10/19/2005 | | PASS |
|
|
|
Plan Modification. Approved pending field inspection of fire alarm permit comments. A single firemans hat is requried for input to each elevator.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/19/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/19/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/19/2005 | | 10/19/2005 | | DONE |
|
|
|
|
Telephone call | | | 10/19/2005 | | DONE |
|
|
|
Left voice message for Kurt that permit is ready & fees///10/19/05 4:05pm BAS
|
Plan resubmittals received | | | 10/6/2005 | | |
|
|
|
|
Miscellaneous action | | | 7/22/2005 | | DONE |
|
|
|
NOTE TO INSPECTOR: The matrix incorrectly defines the elevator control voltage as a "trouble" signal. Per 72 it should be a "supervisory". Sorry for the miss.
|
Inspection Record Card- Fire | 6/3/2005 | | 6/3/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/3/2005 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 6/3/2005 | | DONE |
|
|
|
customer came to pickup plans
|
Plan assigned to (Mary) | 2/9/2005 | | 6/2/2005 | | DONE |
|
|
|
|
Alarm Plan Check | | | 6/2/2005 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/2/2005 | | DONE |
|
|
|
|
Telephone call | | | 5/31/2005 | | DONE |
|
|
|
Phone call to Nick @ Synergy.
Location of the FSA on 9th, the address is 850 Broad. He will find the location of the knox box and move the FSA.
Foster Basement floorplan indicates the elevator stops, but no recall smoke detector and the "elevator machine room" (located in the pit) is shown on the first floor of BODO #4.
Matrix needs to be revised.
Nick will get back to me.
|
Plan resubmittals received | | | 5/25/2005 | | DONE |
|
|
|
|
Alarm Plan Check | | | 2/23/2005 | | FAIL |
|
|
|
Resubmittal required. Faxed comments to Kurt Lechtenberg 2/23.
|
Application received | | | 2/9/2005 | | |
|
|
|
|
Case Summary | | | 2/9/2005 | | DONE |
|
|
|
|