Permit Information
Permit NumberFIR05-00077
StatusFinaled
Name CUSTOM ELECTRIC
Site Address 1212 N HARTMAN ST
Project Namealm - Bench Sewer District
Customer Number 
ePlanReview 
Description
To upgrade the existing fire alarm control panel to provide "supervised" alarm, supervisory and trouble signals to a SCADA system to be transmitted via radio to a constantly attended location. (actually two constantly attended (24/7) locations, Lander St. Waste Water Treatment Plant (to be referred to as "Lander".) and the Utility Maintenance Bldg on Liberty St. (to be referred to as "Liberty".) Approval dated 3/26/2004, from Dave Miller (BFD Fire Marshall) to Bill Freeman (Boise Public Works) to proceed (with conditions) is included in the permit package. The existing fire alarm system is a required sprinkler monitoring system.

There is no associated building permit.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/6/20104/7/20104/7/2010APASS
DetailsTroy Cobbley
Inspection was performed by Mary.
FIR-Aging Inspection4/1/20104/1/20104/6/2010 PASS
DetailsTroy Cobbley
Inspection was performed by Mary.
INSP-Final Inspection9/9/20059/9/20059/12/2005PCANC
DetailsTroy Cobbley
Inspection performed by Mary, see history
INSP-Final Inspection9/6/20059/6/20059/6/2005PCANC
DetailsForrest France
system has been tested -todd; Phone #: ###-#### Inspection has been rescheduled for 9/7/05 per agreement with Todd.
Alarm Plan Check  7/18/2005 PASS
Approved pending field inspection of fire alarm permit comments.
PLANS/APPL TAKEN TO FRONT DESK  7/18/2005 DONE
Permit Ready to Issue  7/18/2005 DONE
Inspection Record Card- Fire7/18/2005 7/18/2005 DONE
Telephone call  7/18/2005 DONE
Spoke with Ken and told him that permit is ready & fees///7/18/05 9:05am BAS
Issue and Print Permit  7/18/2005 DONE
Plan assigned to (Mary)2/9/2005 7/18/2005 DONE
Plan resubmittals received  7/11/2005 DONE
Miscellaneous action  3/1/2005 DONE
Reviewed Dave Miller's e-mail dated 3/26/2004 which stipulates that an FA alarm contractor must be involved. I left a message for Bill Freeman (BPW) that they would need to get a contractor
Plan resubmittals received  2/24/2005 DONE
Received e-mail that included the battery calculations for the RTU.
Telephone call  2/22/2005 DONE
Todd ALder called to see if I had received the information via e-mail. I stated I had not, he woul dresend it.
Telephone call  2/16/2005 DONE
Left a message for Todd Alder, as a reminder to send battery calculations for the RTU.
Application received  2/9/2005  
Case Summary  2/9/2005