INSP-Final Inspection | 4/20/2005 | 4/21/2005 | 4/21/2005 | A | PASS |
Forrest France
|
|
|
Overhead fire sprinkler rough-in pass. Flow req. verified. Additional rack sprinklers on separate permit not installed.
|
INSP-Final Inspection | 4/19/2005 | 4/20/2005 | 4/20/2005 | P | FAIL |
Troy Cobbley
|
|
|
Could not get the required pressure to pass forward flush test. Still need to verify sprinkler spacing as noted on previous inspection
|
Meeting | | | 4/19/2005 | | DONE |
|
|
|
2:50pm, Met with Sam Rogers regarding offsets creating overspacing of 100.2 sf instead of the maximum allowable 100-ft/2 (calcs show 99-ft/2, but pressures and density calc's were for 100 sq ft) spacing (high piled combustible storage-standard heads). He indicated he would accept the code deficiency. JWA
|
INSP-Sprinkler Rough-in/Hydro | 4/18/2005 | 4/18/2005 | 4/18/2005 | P | FAIL |
Troy Cobbley
|
|
|
Multiple branchlines have been relocated and now appear to exceed 99 sq.ft. max. spacing. Provide verification that afcon 303 rings have been used for the trapeze hangers. Provide flexible cplings at the top and bottom of the risers at the inracks. Provid
|
INSP-Conference | 4/15/2005 | 4/18/2005 | 4/18/2005 | A | FAIL |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 4/15/2005 at 2:18:57 PM. Contact: ###-####. No body at the site for the conference. I called Treasure Valley's office prior to showing up but the lady who answered the phone wasn't sure who I needed to talk
|
INSP-Sprinkler Rough-in/Hydro | 4/13/2005 | 4/14/2005 | 4/14/2005 | A | PASS |
Forrest France
|
|
|
Overhead hydro. test passed. Rough-in OK for TI office space only.
|
INSP-Sprinkler Rough-in/Hydro | 4/11/2005 | 4/12/2005 | 4/12/2005 | A | FAIL |
Forrest France
|
|
|
Hydro. AG not ready for test, Rough in fail; need proper temp. heads in storage room, Upright in break room is too far below deck, Upright heads in office and open office are blocked by ductwork in some locations.
|
Issue and Print Permit | | | 4/8/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 3/21/2005 | | 4/7/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/7/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 4/7/2005 | | 4/7/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/7/2005 | | DONE |
|
|
|
|
Telephone call | | | 4/7/2005 | | DONE |
|
|
|
tlk to jeffrey packham ###-#### that permit and fees are ready to be picked up
|
Plan assigned to (Bill) | 3/1/2005 | | 4/7/2005 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/31/2005 | | |
|
|
|
|
Telephone call | | | 3/30/2005 | | DONE |
|
|
|
tlk to receptionist that permit has failed and needs to be picked up
|
Sprinkler Plan Check | 3/22/2005 | | 3/29/2005 | | FAIL |
Bill Alexander
|
|
|
Resubmitted calculations have changed and are now flawed. Designer has modified density with actual spacing for each individual head. Fire sprinklers throughout a facility cannot be adjusted to balance the design for the actual spacing/density installed in this fashion since it will create flawed calculation results. This design verification does not meet the requirements of 14.4.4.4.1, starting with the most remote head per 14.4.4.4.5 and following it back. Revise and resubmit.
|
Plan resubmittals received | | | 3/22/2005 | | DONE |
|
|
|
|
Telephone call | | | 3/9/2005 | | DONE |
|
|
|
left mess that plans failed and return to sender
|
Sprinkler Plan Check | 3/1/2005 | | 3/8/2005 | | FAIL |
Bill Alexander
|
|
|
The data has been moved to a Word document attached to this case.
|
Miscellaneous action | | | 3/8/2005 | | DONE |
|
|
|
Returned failed documents/plans to permit desk for returning.
|
Case Summary | | | 3/1/2005 | | |
|
|
|
|
Application received | | | 3/1/2005 | | |
|
|
|
|