Permit Information
Permit NumberFIR05-00121
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 12450 W EXECUTIVE DR
Project NameSPR MIDWEST FLOOR COVERING
Customer Number 
ePlanReview 
Description
(MIDWEST FLOOR COVERING)(VAN AUKER CLOVERDALE #10 BLDG) To install a complete overhead fire protection (sprinkler) system in a new 26,400-ft/2 shell building with a new tenant to occupy the entire warehouse with a new 1,660-ft/2 accessory office area with a (light) storage mezzanine (above) and a small 144-ft/2 H-3 occupancy flammable liquid storage room. The fire sprinkler work is related to the new shell constructed under BLD03-01306, the new tenant mezzanine with stairway, with two new offices and restrooms, with a breakroom beneath all with suspended ceilings, a new H-3 occupancy flammable liquids storage room along with racking in the warehouse (to be constructed under a separate building permit). This building is fully fire sprinklered. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. The shell building permit was BLD03-01306. Fire underground fire service supply was installed under FIR04-00643. This associated overhead fire sprinkler work permit is attached to building permit: BLD04-02971.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/20/20054/21/20054/21/2005APASS
DetailsForrest France
Overhead fire sprinkler rough-in pass. Flow req. verified. Additional rack sprinklers on separate permit not installed.
INSP-Final Inspection4/19/20054/20/20054/20/2005PFAIL
DetailsTroy Cobbley
Could not get the required pressure to pass forward flush test. Still need to verify sprinkler spacing as noted on previous inspection
Meeting  4/19/2005 DONE
2:50pm, Met with Sam Rogers regarding offsets creating overspacing of 100.2 sf instead of the maximum allowable 100-ft/2 (calcs show 99-ft/2, but pressures and density calc's were for 100 sq ft) spacing (high piled combustible storage-standard heads). He indicated he would accept the code deficiency. JWA
INSP-Sprinkler Rough-in/Hydro4/18/20054/18/20054/18/2005PFAIL
DetailsTroy Cobbley
Multiple branchlines have been relocated and now appear to exceed 99 sq.ft. max. spacing. Provide verification that afcon 303 rings have been used for the trapeze hangers. Provide flexible cplings at the top and bottom of the risers at the inracks. Provid
INSP-Conference4/15/20054/18/20054/18/2005AFAIL
DetailsTroy Cobbley
Scheduled by a contractor via Hello! on 4/15/2005 at 2:18:57 PM. Contact: ###-####. No body at the site for the conference. I called Treasure Valley's office prior to showing up but the lady who answered the phone wasn't sure who I needed to talk
INSP-Sprinkler Rough-in/Hydro4/13/20054/14/20054/14/2005APASS
DetailsForrest France
Overhead hydro. test passed. Rough-in OK for TI office space only.
INSP-Sprinkler Rough-in/Hydro4/11/20054/12/20054/12/2005AFAIL
DetailsForrest France
Hydro. AG not ready for test, Rough in fail; need proper temp. heads in storage room, Upright in break room is too far below deck, Upright heads in office and open office are blocked by ductwork in some locations.
Issue and Print Permit  4/8/2005 DONE
Sprinkler Plan Check3/21/2005 4/7/2005 PASS
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  4/7/2005 DONE
Inspection Record Card- Fire4/7/2005 4/7/2005 DONE
Permit Ready to Issue  4/7/2005 DONE
Telephone call  4/7/2005 DONE
tlk to jeffrey packham ###-#### that permit and fees are ready to be picked up
Plan assigned to (Bill)3/1/2005 4/7/2005 DONE
Plan resubmittals received  3/31/2005  
Telephone call  3/30/2005 DONE
tlk to receptionist that permit has failed and needs to be picked up
Sprinkler Plan Check3/22/2005 3/29/2005 FAIL
DetailsBill Alexander
Resubmitted calculations have changed and are now flawed. Designer has modified density with actual spacing for each individual head. Fire sprinklers throughout a facility cannot be adjusted to balance the design for the actual spacing/density installed in this fashion since it will create flawed calculation results. This design verification does not meet the requirements of 14.4.4.4.1, starting with the most remote head per 14.4.4.4.5 and following it back. Revise and resubmit.
Plan resubmittals received  3/22/2005 DONE
Telephone call  3/9/2005 DONE
left mess that plans failed and return to sender
Sprinkler Plan Check3/1/2005 3/8/2005 FAIL
DetailsBill Alexander
The data has been moved to a Word document attached to this case.
Miscellaneous action  3/8/2005 DONE
Returned failed documents/plans to permit desk for returning.
Case Summary  3/1/2005  
Application received  3/1/2005