INSP-Alarm Testing | 4/12/2005 | 4/12/2005 | 4/13/2005 | P | CANC |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 4/12/2005 at 9:54:23 AM. Contact: ###-####.
|
INSP-Final Inspection | 4/13/2005 | 4/13/2005 | 4/13/2005 | P | PASS |
Troy Cobbley
|
|
|
Fire alarm finaled
|
INSP-Alarm Testing | 4/7/2005 | 4/8/2005 | 4/8/2005 | P | FAIL |
Troy Cobbley
|
|
|
Contact: ###-####. Two a/v's are mounted too high. Tested devices and they operated ok but will need to retest to verify the relocated two still operate
|
Issue and Print Permit | | | 3/31/2005 | | DONE |
|
|
|
|
Plan assigned to (Mary) | 3/15/2005 | | 3/29/2005 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/29/2005 | | DONE |
|
|
|
Received revised matrix and cutsheets for the sync module via fax.
|
Alarm Plan Check | | | 3/29/2005 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/29/2005 | | DONE |
|
|
|
|
Case Summary | | | 3/29/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/29/2005 | | 3/29/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/29/2005 | | DONE |
|
|
|
|
Telephone call | | | 3/29/2005 | | DONE |
|
|
|
tlk to kevin ###-#### that permit and fees are ready to be picked up
|
Telephone call | | | 3/28/2005 | | DONE |
|
|
|
Phoned John Lopez at Fire Sentry to request a revised matrix and sync module cut sheets. He stated he would get them faxed right over.
|
Plan resubmittals received | | | 3/25/2005 | | |
|
|
|
received 2 additional sets of plans
|
Alarm Plan Check | | | 3/23/2005 | | FAIL |
|
|
|
No comments written. Resubmittal is required due to a synchronization of visual appliances in the space. John Lopez has been notified and will revise plans and calcs to reinsert into the existing submittals.
|
Application received | | | 3/15/2005 | | |
|
|
|
|