INSP-Final Inspection | 5/23/2005 | 5/24/2005 | 5/24/2005 | P | PASS |
Forrest France
|
|
|
Fire sprinkler finaled.
|
INSP-Sprinkler Rough-in/Hydro | 5/24/2005 | 5/24/2005 | 5/24/2005 | P | PASS |
Forrest France
|
|
|
Overhead hydrostatic test of spray room supply and branch lines passed inspection.
|
INSP-Final Inspection | 5/20/2005 | 5/23/2005 | 5/23/2005 | P | FAIL |
Forrest France
|
|
|
Pendent heads in hallway need to match response rating per NFPA 13 8.3.3.2. Upright heads above spray room are overspaced, need to meet 130 sq foot req. Perform hydrostatic test per. review notes.
|
INSP-Final Inspection | 5/3/2005 | 5/4/2005 | 5/4/2005 | A | CANC |
Forrest France
|
|
|
Cancel inspection per general contractor, not ready..
|
INSP-Final Inspection | 5/2/2005 | 5/3/2005 | 5/3/2005 | P | CANC |
Troy Cobbley
|
|
|
harry; Phone #: ###-#### Ran out of time to do inspection.
|
INSP-Sprinkler Rough-in | 4/18/2005 | 4/18/2005 | 4/18/2005 | P | FAIL |
Forrest France
|
|
|
Fail inspection, fire sprinkler changes in spray booth and exterior compressor room not completed.
|
INSP-Final Inspection | 4/14/2005 | 4/15/2005 | 4/15/2005 | A | FAIL |
Forrest France
|
|
|
Re-submitted approved plans and notes not available for review. Job supervisor seeks temp. occupancy approval.
|
Telephone call | | | 4/15/2005 | | DONE |
|
|
|
tlk to secretary ###-#### 4/14/2005 2nd rev is ready to be picked up no fee
|
Sprinkler Plan Check | 4/4/2005 | | 4/14/2005 | | PASS |
Bill Alexander
|
|
|
|
Miscellaneous action | | | 4/14/2005 | | DONE |
|
|
|
Took corrected/revised plans to front desk for releasing.
|
Plan resubmittals received | | | 4/4/2005 | | |
|
|
|
|
Issue permit | | | 3/30/2005 | | |
|
|
|
|
Plan assigned to (Bill) | 3/21/2005 | | 3/29/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 3/21/2005 | | 3/29/2005 | | PART |
Bill Alexander
|
|
|
1. Standard sprinklers or automatic spray nozzles shall be so located as to provide for the protection of exhaust ducts, hood exhaust duct collars, and hood exhaust plenum chambers. Each hood exhaust duct collar shall have one sprinkler or automatic spray nozzle located 1" minimum to 12" maximum above the point of duct collar connection in the hood plenum. Horizontal exhaust ducts shall have sprinklers or automatic spray nozzle devices located on 10'-0" centers beginning no more than 5'-0" from the duct entrance. Modify spacing/layout/location. Add a sprinkler head to within 1" to 12" of the exhaust plenum chamber. (NFPA 13-7.9.3.3, 7.9.4.1, 7.9.2.1)
2. The permit scope of work does not address and work relating to the compressor room? Provide plans that address protecting this addition. BMC 7-01-50-IFC 901.2, 105.4.2)
3. Sprinklers or automatic spray nozzles being used in duct, duct collar, and plenum areas shall have orifice with K-factors not less than 1.4 and not more than 5.6. Modify sprinkler heads in the ducts to conform to this paragraph. (NFPA 13-7.9.6.3)
4. Access shall be provided to all sprinklers or automatic spray nozzles for examination and replacement. Provide service openings for fire sprinkler head examination which shall meet the minimum requirements of IMC for duct access penetrations. NOTE: Duct supports shall be designed to carry the weight of the duct system itself, plus the anticipated weight of any residues. If sprinkler protection is provided inside the duct system, then the duct supports also shall be designed to carry the anticipated weight of any accumulation of sprinkler discharge. (NFPA 33-7.8.1, 7.9.7)
5. The sprinklers for each spray area and mixing room shall be controlled by a separate, accessible, listed indicating valve. Sprinkler systems in stacks or ducts shall be automatic and of a type not subject to freezing. Fire sprinkler control valve handles must be installed between two (2'-0") and five (5'-0") feet above finished grade. (IFC 102.7, NFPA 33-9.4.5, NFPA 13-13.4.2.1*)
6. Address on the plans that the fire sprinklers shall be covered by cellophane bags having a thickness of 0.08 mm (0.003 in.) or less or by thin paper bags. These coverings shall be replaced frequently so that heavy deposits of residue do not accumulate. (NFPA 33-9.4.7.1, 13-6.2.6.4.2, 13.4.2.2)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/29/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/29/2005 | | 3/29/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/29/2005 | | DONE |
|
|
|
|
Telephone call | | | 3/29/2005 | | DONE |
|
|
|
tlk to receptionist ###-#### that permit and fees are ready to be picked up
|