Permit Information
Permit NumberFIR05-00162
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 10500 W OVERLAND RD
Project NameSPR ALBERSTON STORE #160-1
Customer Number 
ePlanReview 
Description
ALBERTSONS STORE #0160-FIVE MILE PLAZA (PHASE 1 & 2)
PHASE 1: Phase 1 is fire sprinkler protection work is a limited to removal of approximately 3-4 fire sprinklers in the bakery and 3-4 in the Deli to accommodate the demolition of existing ceilings in the phased remodel to an existing 49,371-ft/2 grocery store building located at the west end of an existing shopping center. The roof protection system in place shall protect the floor area associated with the affected work.
PHASE 2: Phase 2 is relocating and adding fire sprinkler protection in the new Pharmacy, Customer Service, Front Canopy, Meat Preparation, Bakery Production and Freezers & Coolers in the phased remodel to an existing 49,371-ft/2 grocery store. This building was constructed in Ada County in 1978 and annexed into Boise City on 12/30/99. This building is fully fire sprinklered for area increase. The fire sprinkler system work shall comply with IFC 2000, attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD4-02214.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/11/20061/11/20061/11/2006PPASS
DetailsTroy Cobbley
permit finaled
INSP-Final Inspection12/8/200512/9/200512/9/2005PPART
DetailsForrest France
The two added heads in the bakery to meet correct spacing requirements are satisfactory.
INSP-Final Inspection12/6/200512/7/200512/7/2005PFAIL
DetailsTroy Cobbley
Heads are overspaced in the bakery. Provide two additional heads as discussed.
INSP-Final Inspection9/29/20059/30/20059/30/2005PFAIL
DetailsTroy Cobbley
Revised plans not on site. No inspection done
Inspection Record Card- Fire6/21/2005 6/21/2005 DONE
CHANGE STATUS TO (ISS)  6/21/2005 DONE
Sprinkler Plan Check6/10/2005 6/20/2005 PASS
DetailsBill Alexander
6/10/2005 - Don Weland submitted changed sprinkler heads installed which are recalled by the manufacturer. Emailed response indicating they are not accepted.
6/15/2005 - Don Weland submitted revised manufacturer data submittals only. Requested:
1. Submit with a permit application (resubmittal) with revised scope of work indicating what you are now doing,
2. Include which manufacturer sprinkler model identified you are, or did install, since more than one is listed in the data,
3. Include revised sprinkler schedule & legend/s with symbols, SIN, description, type K-factor, temp, escutcheon and quantities, etc.
4. Two plans were submitted and each plan had legends. If each plan incorporated changes, then provide those changes for each,
5. Fax it to: ###-####.

6/15/2005
Recieved revised drawings.
Plan assigned to (Bill)6/10/2005 6/20/2005 DONE
DetailsBill Alexander
Plan assigned to (Bill)6/15/2005 6/20/2005 DONE
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  6/20/2005 DONE
PLANS/APPL TAKEN TO FRONT DESK  6/20/2005 DONE
Permit Ready to Issue  6/20/2005 DONE
Telephone call  6/20/2005 DONE
tlk to trent bice ###-#### that permit and fees are ready to be picked up
Plan resubmittals received  6/15/2005 DONE
Case Summary  6/15/2005 DONE
INSP-Final Inspection6/3/20056/6/20056/6/2005AFAIL
DetailsTroy Cobbley
See city approved plans for locations of defiencies which include overspaced heads in the pharmacy and customer service/video rental
Issue permit  5/25/2005  
Permit Ready to Issue  5/24/2005  
Inspection Record Card- Fire5/24/2005 5/24/2005 DONE
Telephone call  5/24/2005 DONE
left mess that permit is ready
Sprinkler Plan Check5/12/2005 5/23/2005 PASS
DetailsBill Alexander
Telephone call  5/23/2005 DONE
8:55am. Talked to "Chip" (John Armstrong) and requested he submit firew sprinkler head legend (FP-1) that matches the sprinklers installing (no correlation) and fax to: ###-####.
Plan assigned to (Bill)5/12/2005 5/23/2005 DONE
PLANS/APPL TAKEN TO FRONT DESK  5/23/2005 DONE
Plan resubmittals received  5/12/2005 DONE
INSP-Sprinkler Rough-in5/9/20055/10/20055/10/2005PFAIL
DetailsTroy Cobbley
Inspection stopped. No approval notes for plans. Head not shown on plans that has been installed under the overhead door. Dry pendants in coolers are Viking, not Central as shown on the plans. Pendant heads in the meat dept. are SIN3231 which are not the
INSP-Sprinkler Rough-in5/10/20055/10/20055/10/2005PFAIL
DetailsTroy Cobbley
This entry is a supplement to the earlier entry. Pendant heads in the meat department that have been changed out are not shown on the approved plans as part of the work.
INSP-Sprinkler Rough-in5/10/20055/10/20055/10/2005PFAIL
DetailsTroy Cobbley
This entry is a supplement to the earlier entry. Pendant heads in the meat department that have been changed out are not shown on the approved plans as part of the work.
Sprinkler Plan Check4/26/2005 5/3/2005 PASS
DetailsBill Alexander
Plan assigned to (Bill)4/26/2005 5/3/2005 DONE
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  5/3/2005 DONE
Inspection Record Card- Fire5/3/2005 5/3/2005 DONE
Permit Ready to Issue  5/3/2005 DONE
Telephone call  5/3/2005 DONE
called spoke with chip permit is ready and fees 5/3/05 3:11pm LEM
Issue and Print Permit  5/3/2005 DONE
Plan resubmittals received  4/26/2005 DONE
Inspection Record Card- Fire3/24/2005 3/24/2005 DONE
Permit Ready to Issue  3/24/2005 DONE
Telephone call  3/24/2005 DONE
tlk to trent ###-#### that permit and fees are ready to be picked up
Case Summary  3/24/2005 DONE
Issue and Print Permit  3/24/2005 DONE
Application received  3/23/2005  
Plan assigned to (Bill)3/23/2005 3/23/2005 DONE
Sprinkler Plan Check3/23/2005 3/23/2005 PASS
DetailsBill Alexander
Faxed permit application
PLANS/APPL TAKEN TO FRONT DESK  3/23/2005 DONE