INSP-Final Inspection | 3/13/2006 | 3/14/2006 | 3/15/2006 | P | PASS |
Forrest France
|
|
|
c/n items have been completed, EOL's tested, signals verified, inspection passed. Permit finaled.
|
INSP-Final Inspection | 3/2/2006 | 3/8/2006 | 3/9/2006 | P | FAIL |
Forrest France
|
|
|
Provide access to "Moxie Java" tenant space for EOL test and verification of notification in the work room, replace non-functional a/v in the "Varsity Grill" and test EOL, one strobe in the ground level airport operation 1 maintenance room is blocked by adjacent cabinets, tested performance and audibility of notification in the ground and second levels, tested detectors at the WON and fire doors for release.
|
INSP-Conference | 3/3/2006 | 3/6/2006 | 3/6/2006 | A | DONE |
Forrest France
|
|
|
On site confrence to discuss a/v notification location requirements for concoure B.
|
INSP-Final Inspection | 2/20/2006 | 2/24/2006 | 2/24/2006 | A | FAIL |
Forrest France
|
|
|
Tested pull stations, duct smoke detectors, smoke alarms and verified Cd rating and spacing on av notification devices on the ground and first floor concourse B, the wall mounted notification appliances installed under this permit are below the min. height allowed per NFPA 72 2002 7.5.4 for the lens portion, still need to test functionality and performance of the notification devices, EOL drop, signal verification, etc.
|
Issue and Print Permit | | | 11/4/2005 | | DONE |
|
|
|
|
Alarm Plan Check | | | 10/28/2005 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/28/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/28/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/28/2005 | | 10/28/2005 | | DONE |
|
|
|
|
Telephone call | | | 10/28/2005 | | DONE |
|
|
|
Spoke with Charie and told him that permit is ready & fees///10/28/05 1:30pm BAS
|
Plan assigned to (Mary) | 4/1/2005 | | 10/28/2005 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/14/2005 | | DONE |
|
|
|
|
Telephone call | | | 10/4/2005 | | DONE |
|
|
|
Called Chris WIllis then I faxed over the comments.
|
Alarm Plan Check | | | 10/4/2005 | | FAIL |
|
|
|
Faxed comments to Chris Willis. They will resubmit
|
Plan resubmittals received | | | 9/20/2005 | | DONE |
|
|
|
|
Case Summary | | | 9/20/2005 | | DONE |
|
|
|
|
Meeting | | | 6/10/2005 | | DONE |
|
|
|
Meeting with M. Pataja, and all related trades regarding scope of the alarm upgrade project. It was agreed that the airport would have the existing FA systems evaluated to determine if they met the code under which they were installed and if they did, compare the cost to extending the existing systems to the option of designing to match the system as installed in the new terminal. It was agreed they could proceed with installation of a/v annunciation appliances as shown on submitted plans without approved plans or a permit on site, subject to the agreement that revised plans for the detection devices will be forthcoming and that approved plans and a permit will be on site prior to installation of the detection devices. Final inspection will be based on the approved plans issued with the permit.
|
Alarm Plan Check | | | 5/24/2005 | | FAIL |
|
|
|
Resubmittal required. No manual pull stations are shown on the ground floor.
|
Plan resubmittals received | | | 5/17/2005 | | DONE |
|
|
|
|
Alarm Plan Check | | | 4/15/2005 | | FAIL |
|
|
|
Resubmittal Required.
|
Application received | | | 4/1/2005 | | |
|
|
|
|