INSP-Final Inspection | 3/13/2006 | 3/14/2006 | 3/15/2006 | P | PASS |
Forrest France
|
|
|
Items on c/n have been completed, signals verified, EOL tested, inspection passed. Permit finaled.
|
INSP-Final Inspection | 3/8/2006 | 3/9/2006 | 3/9/2006 | A | FAIL |
Forrest France
|
|
|
One a/v in the "Varsity Grill" is non-functional, need to test the EOL at this location, address the required corrections for the concourse B as discussed, previous c/n items have been completed.
|
INSP-Final Inspection | 3/2/2006 | 3/8/2006 | 3/8/2006 | A | DEFR |
Forrest France
|
|
|
Robert; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong Inspection to be completed early am on 3/9 as discussed.
|
INSP-Final Inspection | 2/20/2006 | 2/24/2006 | 2/24/2006 | A | PART |
Forrest France
|
|
|
Duct smoke detector tested okay, verified av Cd ratings and spacing, the functionality test pending after hours inspection for audibility and performance, the av's in the adjacent hall are below min. height requirements for the strobe lens.
|
Issue and Print Permit | | | 11/4/2005 | | DONE |
|
|
|
|
Alarm Plan Check | | | 10/28/2005 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/28/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/28/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/28/2005 | | 10/28/2005 | | DONE |
|
|
|
|
Telephone call | | | 10/28/2005 | | DONE |
|
|
|
Spoke with Charie and told him that permit is ready & fees///10/28/05 1:30pm BAS
|
Plan assigned to (Mary) | 4/1/2005 | | 10/28/2005 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/14/2005 | | DONE |
|
|
|
|
Alarm Plan Check | | | 10/4/2005 | | FAIL |
|
|
|
Faxed comments to Chris Willis. They will resubmit
|
Plan resubmittals received | | | 9/20/2005 | | DONE |
|
|
|
|
Case Summary | | | 9/20/2005 | | DONE |
|
|
|
|
Meeting | | | 6/7/2005 | | DONE |
|
|
|
Meeting with M. Pataja, and all related trades regarding scope of the alarm upgrade project. It was agreed that the airport would have the existing FA systems evaluated to determine if they met the code under which they were installed and if they did, compare the cost to extending the existing systems to the option of designing to match the system as installed in the new terminal. It was agreed they could proceed with installation of a/v annunciation appliances as shown on submitted plans without approved plans or a permit on site, subject to the agreement that revised plans for the detection devices will be forthcoming and that approved plans and a permit will be on site prior to installation of the detection devices. Final inspection will be based on the approved plans issued with the permit.
|
Plan resubmittals received | | | 5/17/2005 | | DONE |
|
|
|
|
Application received | | | 4/1/2005 | | |
|
|
|
|