DOC - Permit Finaled | | | 2/28/2006 | | DONE |
|
|
|
per inspection by 430 on 1-25-06
|
INSP-Alarm Testing | 1/19/2006 | 1/25/2006 | 1/25/2006 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Alarm Testing | 11/15/2005 | 11/22/2005 | 11/22/2005 | A | CANC |
Troy Cobbley
|
|
|
No time for inspection
|
Plan assigned to (Mary) | 4/13/2005 | | 6/3/2005 | | DONE |
|
|
|
|
Alarm Plan Check | | | 6/3/2005 | | PASS |
|
|
|
Approved pending PDS Fire Inspector field verification. No comments written.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/3/2005 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/3/2005 | | DONE |
|
|
|
|
Telephone call | | | 5/31/2005 | | DONE |
|
|
|
Paul Marcolina will be sending out an update on Wednesday afternoons to all four (4) of us at the city. This will advise us if we have reviews to do at the site. Apparently this permit was ready for second review on last Friday, but no one notified me that it was ready. It will get reviewed on 6/3.
|
Case Summary | | | 5/13/2005 | | DONE |
|
|
|
|
Miscellaneous action | | | 5/13/2005 | | DONE |
|
|
|
Checked the hanging plans, no changes are included, permit not ready for re-review.
|
Alarm Plan Check | | | 5/6/2005 | | FAIL |
|
|
|
Clarification required on the following:
1) Fire alarm permit application needs to be completed to define the system and occupancy of the TI. (I will call John W. James to discuss the obivious information that need not be included.)
2) Ceiling height (according to the mechanical section (M4.1?), there is NO ceiling. Provide the appropriate mounting height, detail for mounting and candela for total coverage of the space. (Have you taken into consideration the height of the tool?)
3) Corridor at the south end does not indicate any notification coverage. Provide revised information to include new or existing coverage.
|
Application received | | | 4/13/2005 | | |
|
|
|
|