INSP-Final Inspection | 8/23/2005 | 8/23/2005 | 8/23/2005 | P | PASS |
Forrest France
|
|
|
Calculations for spacing have been verified. Fire sprinkler permit finaled.
|
Plan assigned to (Bill) | 8/19/2005 | | 8/23/2005 | | DONE |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/23/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/23/2005 | | 8/23/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/23/2005 | | DONE |
|
|
|
|
Issue and Print Permit | | | 8/23/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/19/2005 | | 8/23/2005 | | PASS |
Bill Alexander
|
|
|
Major pipe modification and revised head spacing calculation verifications.
|
INSP-Final Inspection | 8/19/2005 | 8/19/2005 | 8/19/2005 | P | FAIL |
Troy Cobbley
|
|
|
Still need to verify that the sprinkler spacing in the conference room and the additional dry pendants are approved with resubmittals.
|
Plan resubmittals received | | | 8/19/2005 | | DONE |
|
|
|
|
INSP-Final Inspection | 8/17/2005 | 8/17/2005 | 8/17/2005 | P | FAIL |
Troy Cobbley
|
|
|
Forward flush passed but need to certify the backflow preventor, provide verification of the spacing in the conference room and the additional dry pendants with bill as previously requested. Verify that the valve for the ball drip in the pit is open
|
INSP-Sprinkler Rough-in/Hydro | 7/7/2005 | 7/7/2005 | 7/7/2005 | P | PASS |
Troy Cobbley
|
|
|
Wet system hydro test passed. Sprinkler piping is ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 6/29/2005 | 6/30/2005 | 6/30/2005 | P | PASS |
Troy Cobbley
|
|
|
24 hour air test passed on dry system
|
INSP-Sprinkler Rough-in/Hydro | 6/29/2005 | 6/29/2005 | 6/29/2005 | P | PART |
Troy Cobbley
|
|
|
Started 24 hour air test with 50psi on guage.
|
INSP-Sprinkler Rough-in/Hydro | 6/16/2005 | 6/16/2005 | 6/16/2005 | P | PASS |
Troy Cobbley
|
|
|
200 lb hydro test on the dry pipe system passed.
|
INSP-Sprinkler Rough-in/Hydro | 6/7/2005 | 6/7/2005 | 6/7/2005 | P | PART |
Troy Cobbley
|
|
|
The remaining part of the dry system passed. Not all arm overs have been installed and will need inspected. Final head spacing to be checked when t-bar is installed.
|
INSP-Sprinkler Rough-in/Hydro | 6/3/2005 | 6/3/2005 | 6/3/2005 | P | PART |
Troy Cobbley
|
|
|
See city approved plans for location where wet system can be covered as of 6/3/05.
|
INSP-Sprinkler Rough-in/Hydro | 6/1/2005 | 6/1/2005 | 6/1/2005 | P | PART |
Troy Cobbley
|
|
|
The dry system rough-in is ok except for one head needs to be added in the south east room. Contractor needs to get with Bill Alexander to see if a resubmittal will be required for this head and the three other dry uprights added at each of the entrances.
|
Sprinkler Plan Check | 5/20/2005 | | 5/31/2005 | | PASS |
Bill Alexander
|
|
|
05/27/2005 8:00am-Email to Jeff Anderson:
Requested completed calc cover sheets.
Requested information on where plan changes were made in this project.
05/31/2005 11:15am-Converstation with John Graves.
|
Plan assigned to (Bill) | 5/20/2005 | | 5/31/2005 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/31/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/31/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/31/2005 | | 5/31/2005 | | DONE |
|
|
|
|
Telephone call | | | 5/31/2005 | | DONE |
|
|
|
Spoke with Jeff Anderson and told him that permit is ready & fees///5/31/05 1:10pm BAS
|
Issue and Print Permit | | | 5/31/2005 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/20/2005 | | |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 5/19/2005 | 5/19/2005 | 5/19/2005 | P | PART |
Troy Cobbley
|
|
|
Sprinkler piping in the west drive thru canopy can be covered. As stated in the previous inspection entry, plans need to be resubmitted due to changes.
|
INSP-Supply line flush | 5/17/2005 | 5/17/2005 | 5/17/2005 | P | PASS |
Troy Cobbley
|
|
|
Underground supply line flush and underground hydro test passed. I had contractor measure leakage. 5 1/2 quarts was allowed and it lost approx. 2 1/2 to 3 quarts
|
INSP-Sprinkler Rough-in | 5/17/2005 | 5/17/2005 | 5/17/2005 | P | FAIL |
Troy Cobbley
|
|
|
I started rough-in inspection on the dry system at the request of the onsite sprinkler fitter but could not do the inspection due to pipe routing and sizing not matching approved plans. Upright heads are not spaced in accordance with NFPA 13 for obstruct
|
Issue and Print Permit | | | 4/25/2005 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 4/13/2005 | | 4/22/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 4/21/2005 | | 4/22/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/22/2005 | | DONE |
Bill Alexander
|
|
|
|
Inspection Record Card- Fire | 4/22/2005 | | 4/22/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/22/2005 | | DONE |
|
|
|
|
Telephone call | | | 4/22/2005 | | DONE |
|
|
|
lft ms with secretary for jeff anderson ###-#### that permit and fees are ready to be picked up
|
Sprinkler Plan Check | 4/13/2005 | | 4/21/2005 | | FAIL |
Bill Alexander
|
|
|
1. Provide 3 copies of the manufacturer's data submittals, 4" backflow.
2. Provide 3 copies of the manufacturers data submittals the Dry Pipe Valve (if more than one available on the sheet/s-identify)
3. Provide 3 copies of the manufacturer's data submittals of the "air maintenance device".
4. Provide 3 copies of the manufacturer's data submittals of the "compressor".
5. Attic is identified as "obstructed" with the definition "Wood Joist Construction." This definition is different than "Wood Truss." Relating to you section view on FP3, I do not see wood joists, but I do see wood trusses. Your hanger detail (same sheet) addresses Wood Trusses also? If obstructed, clarify and indicate the affected areas on a plan (minimum 3 - 8½" X 11's), with details where the deflector will be places from the roof. If your have made a mistake, and the wood truss 2" X 4" or 6"s, etc., are the impairment suggesting, then the "3 times rule" will apply.
6. Calc Area #1 is using 11.2.3.2.3 (reduced area of operation), which will require sprinkler protection in all unprotected sprinkler pocket/s. Otherwise revise your calculations with a minimum 1500-ft/2 area of operation and leave the pocket/s unprotected. Correct and resubmit a minimum of 3 (your choice).
|
Plan resubmittals received | | | 4/21/2005 | | |
Bill Alexander
|
|
|
|
Application received | | | 4/13/2005 | | |
|
|
|
|