INSP-Final Inspection | 6/10/2005 | 6/10/2005 | 6/10/2005 | P | PASS |
Forrest France
|
|
|
Fire sprinkler finaled.
|
INSP-Sprinkler Rough-in/Hydro | 6/3/2005 | 6/3/2005 | 6/3/2005 | P | PART |
Forrest France
|
|
|
End 24 hr. air test of dry system overhead piping. Test passed inspection.
|
INSP-Sprinkler Rough-in | 6/2/2005 | 6/2/2005 | 6/2/2005 | P | PART |
Forrest France
|
|
|
Begin 24 hour air test of dry system overhead piping at 12:30 pm.
|
INSP-Sprinkler Rough-in/Hydro | 5/26/2005 | 5/26/2005 | 5/26/2005 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test passed inspection. Still need to perform 24 hr. air test.
|
INSP-Sprinkler Rough-in | 5/26/2005 | 5/26/2005 | 5/26/2005 | P | FAIL |
Forrest France
|
|
|
Provide forward flow apparatus as required by review note #74, provide EQ brace on 4" main north side last piece, provide plans showing two SW heads at overhead door.
|
Issue and Print Permit | | | 5/12/2005 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 4/28/2005 | | 5/9/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 4/28/2005 | | 5/9/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/9/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/9/2005 | | 5/9/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/9/2005 | | DONE |
|
|
|
|
Telephone call | | | 5/9/2005 | | DONE |
|
|
|
lft ms with receptionist ###-#### that permit and fees are ready to be picked up
|
Case Summary | | | 4/28/2005 | | |
|
|
|
|
Application received | | | 4/28/2005 | | |
|
|
|
|