INSP-Final Inspection | 12/5/2005 | 12/5/2005 | 12/5/2005 | A | PASS |
Forrest France
|
|
|
UG fire supply finaled.
|
INSP-Alarm Testing | 11/2/2005 | 11/2/2005 | 11/2/2005 | P | PASS |
Forrest France
|
|
|
Underground fire supply line permit finaled.
|
INSP-Final Inspection | 11/2/2005 | 11/2/2005 | 11/2/2005 | P | CANC |
Forrest France
|
|
|
Duplicate inspection already called in.
|
INSP-Sprinkler Rough-in | 9/14/2005 | 9/15/2005 | 9/16/2005 | P | PART |
Forrest France
|
|
|
First floor lower office sprinkler rough-in is good for cover, also discussed uprights above drop ceiling at second level and garage door coverage in the warehouse area.
|
INSP-Sprinkler Rough-in/Hydro | 6/28/2005 | 6/29/2005 | 6/29/2005 | A | PART |
Forrest France
|
|
|
Underground fire supply passed hydrostatic test. Still need to perform UG flushing.
|
INSP-Sprinkler Rough-in | 6/22/2005 | 6/23/2005 | 6/23/2005 | A | PART |
Forrest France
|
|
|
Underground fire supply line is approved for cover.
|
INSP-Sprinkler Rough-in | 6/21/2005 | 6/22/2005 | 6/22/2005 | A | FAIL |
Forrest France
|
|
|
Fail, underground pipe has been buried prior to inspection for cover. Expose pipe and call for a re-inspect.
|
INSP-Sprinkler Rough-in | 6/16/2005 | 6/16/2005 | 6/16/2005 | P | FAIL |
Forrest France
|
|
|
Underground piping must meet min. depth of bury req. NFPA 10.4.1, backfill at rock per 10.9.4, support per 10.7.9, distance from embankment per 10.5.4, and meet deflection requirements. The pipe laid over the large section of embeded rock in the trench fails to meet code standards and requirements.
|
INSP-Sprinkler Rough-in | 6/13/2005 | 6/13/2005 | 6/13/2005 | P | PART |
Forrest France
|
|
|
Underground fire supply line riser piece and 5' stub out OK to cover. Still need provision for EQ clearance through floor slab.
|
Issue permit | | | 6/6/2005 | | |
|
|
|
|
Plan assigned to (Bill) | 5/3/2005 | | 6/2/2005 | | DONE |
|
|
|
|
Plan resubmittals received | | | 6/2/2005 | | |
|
|
|
|
Sprinkler Plan Check | 6/2/2005 | | 6/2/2005 | | PASS |
Bill Alexander
|
|
|
|
Miscellaneous action | | | 6/2/2005 | | DONE |
|
|
|
Returned documents to the permit desk for returning to sender.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/2/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/2/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/2/2005 | | 6/2/2005 | | DONE |
|
|
|
|
Telephone call | | | 6/2/2005 | | DONE |
|
|
|
called left messge permit is ready and fees
|
Sprinkler Plan Check | 5/3/2005 | | 5/10/2005 | | FAIL |
Bill Alexander
|
|
|
1. Provide information on building underground riser through the floor of the proposed building which includes:
a. Provide pipe type and size of the underground riser extending through the floor of this building.
b. Provide clarification of all fitting, including any installing on the top of the riser.
c. Provide required thrust blocking information (in detail) installing on the riser piping and fitting/s.
d. Include how the piping will pass through the buildings footing or the distance of the top of pipe to bottom of footing.
(BMC 7-01-53-901.2 and IFC 901.2)
2. Provide clarification on why this designer is not including an outside control valve as required in BMC 7-01-53-903.1.3 or addressing an allowed alternative since outside controls should be installed under this type of permit.
|
Telephone call | | | 5/10/2005 | | DONE |
|
|
|
left message for John that plans failed and need picked up///5/10/005 1:25pm BAS
|
Application received | | | 5/3/2005 | | |
|
|
|
|