INSP-Final Inspection | 9/6/2005 | 9/7/2005 | 9/7/2005 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 8/31/2005 | 9/1/2005 | 9/1/2005 | A | FAIL |
Forrest France
|
|
|
Incomplete coverage at front of store next to entryway, upright head is blocked by a soffit below.
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 8/31/2005 | | |
|
|
|
fire inspection
|
INSP-Conference | 8/16/2005 | 8/16/2005 | 8/16/2005 | P | DONE |
Troy Cobbley
|
|
|
I spoke to Jeff at treasuer valley fire and he will follow up on status of the fire sprinkler permit
|
Issue permit | | | 6/9/2005 | | |
|
|
|
|
Sprinkler Plan Check | 6/2/2005 | | 6/7/2005 | | PASS |
Bill Alexander
|
|
|
Field modifications plan corrections.
|
Plan assigned to (Bill) | 6/2/2005 | | 6/7/2005 | | DONE |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/7/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/7/2005 | | |
|
|
|
|
Telephone call | | | 6/7/2005 | | DONE |
|
|
|
left mess that permit is ready
|
Plan resubmittals received | | | 6/2/2005 | | |
|
|
|
|
INSP-Final Inspection | 5/31/2005 | 5/31/2005 | 5/31/2005 | P | PART |
Troy Cobbley
|
|
|
Piping still does not match plans. Per sam rogers a temp is ok until plans have been resubmitted
|
Sprinkler Plan Check | 5/23/2005 | | 5/31/2005 | | PASS |
Bill Alexander
|
|
|
|
Miscellaneous action | | | 5/31/2005 | | DONE |
|
|
|
Took revised plans to permit desk for returning.
|
Inspection Record Card- Fire | 5/31/2005 | | 5/31/2005 | | DONE |
|
|
|
|
Telephone call | | | 5/31/2005 | | DONE |
|
|
|
Spoke with Jeff Anderson and told him that permit is ready & fees///5/31/05 1:10pm BAS
|
(F) Reprint permit | | | 5/31/2005 | | DONE |
|
|
|
|
INSP-Final Inspection | 5/24/2005 | 5/24/2005 | 5/24/2005 | P | CANC |
Troy Cobbley
|
|
|
Per Adam the plans have not been resubmitted yet as requested at the last inspection
|
Plan resubmittals received | | | 5/23/2005 | | DONE |
|
|
|
|
INSP-Final Inspection | 5/20/2005 | 5/20/2005 | 5/20/2005 | P | FAIL |
Troy Cobbley
|
|
|
Resubmit plans showing the correct floor plan, main location, piping size and deletion of head at front of store. Provide sprinkler coverage in the entry since entry soffit and overhead duct combined exceed 4'.
|
INSP-Sprinkler Rough-in/Hydro | 5/18/2005 | 5/19/2005 | 5/19/2005 | A | CANC |
Troy Cobbley
|
|
|
To be done when building is ready to final.
|
Inspection Record Card- Fire | 5/12/2005 | | 5/12/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/12/2005 | | |
|
|
|
|
Issue and Print Permit | | | 5/12/2005 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 5/5/2005 | | 5/11/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 5/5/2005 | | 5/11/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/11/2005 | | DONE |
|
|
|
|
Case Summary | | | 5/5/2005 | | |
|
|
|
|
Application received | | | 5/5/2005 | | |
|
|
|
|