INSP-Final Inspection | 3/29/2007 | 3/30/2007 | 3/30/2007 | A | PASS |
Forrest France
|
|
|
Corrections verified for completion, fire sprinkler passed inspection, permit finaled.
|
INSP-Final Inspection | 3/26/2007 | 3/27/2007 | 3/27/2007 | A | FAIL |
Forrest France
|
|
|
Missing escutcheons at several locations, need to complete forward flow testing with a functional pitot guage.
|
INSP-Sprinkler Rough-in/Hydro | 3/24/2007 | 3/26/2007 | 3/26/2007 | P | PART |
Forrest France
|
|
|
OH hydrostatic test completed satisfactory, noted leakage at the drain connection piping to be repaired prior to next inspection.
|
INSP-Sprinkler Rough-in/Hydro | 12/20/2006 | 12/22/2006 | 12/22/2006 | A | PART |
Forrest France
|
|
|
Approval for overhead fire sprinkler cover on the first and second floors of building #7 only. Third floor will require an inspeciton for cold cavity protection prior to cover.
|
INSP-Sprinkler Rough-in | 12/19/2006 | 12/20/2006 | 12/21/2006 | A | PART |
Troy Cobbley
|
|
|
Sprinkler rough-in is mostly passed. Four overspaced heads were relocated while I performed the inspection. The first floor sprinkler piping can be covered except the garage as marked on the plans where the 1 1/2" main has actually be installed with with 2". Additional heads have been installed in closets that weren't shown in the first floor lobby. The second floor is ok to cover. The third floor can not be covered until a tenting inspection has been performed. Also on the third floor additional heads have been added in the bedrooms. One of these bedrooms is a remote area. Plans need to be resubmitted showing all of the addtional heads and piping reroutes. Also revised hydraulic calculations need to be resubmitted to verify the pipe size change on the first floor and the additional head that may need to be included in the remote area on the third floor.
|
INSP-Sprinkler Rough-in | 12/18/2006 | 12/19/2006 | 12/19/2006 | P | CANC |
Forrest France
|
|
|
No time available to complete this inspection today.
|
INSP-Supply line flush | 12/6/2006 | 12/6/2006 | 12/6/2006 | P | PART |
Forrest France
|
|
|
UG supply line flush completed.
|
INSP-Supply line flush | 11/29/2006 | 11/30/2006 | 11/30/2006 | A | CANC |
Troy Cobbley
|
|
|
bryan was unable to do the flush today
|
INSP-Sprinkler Rough-in/Hydro | 11/29/2006 | 11/30/2006 | 11/30/2006 | A | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed.
|
INSP-Sprinkler Rough-in | 10/31/2005 | 10/31/2005 | 10/31/2005 | P | PASS |
Troy Cobbley
|
|
|
Underground supply piping is ok to cover.
|
CHANGE STATUS TO (ISS) | | | 6/30/2005 | | DONE |
|
|
|
|
(F) Reprint permit | | | 6/30/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 6/24/2005 | | 6/29/2005 | | PASS |
Bill Alexander
|
|
|
Modifications to undergroun on building #8.
R-2 Garage piping modified to protected CPVC.
|
Plan assigned to (Bill) | 6/29/2005 | | 6/29/2005 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/29/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/29/2005 | | DONE |
|
|
|
|
Telephone call | | | 6/29/2005 | | DONE |
|
|
|
tlk to brodie ###-#### that permit and fees are ready to picked up
|
Plan resubmittals received | | | 6/24/2005 | | |
|
|
|
|
Issue and Print Permit | | | 6/7/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 5/26/2005 | | 6/6/2005 | | PASS |
Bill Alexander
|
|
|
|
Plan assigned to (Bill) | 5/26/2005 | | 6/6/2005 | | DONE |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/6/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/6/2005 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/26/2005 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 5/6/2005 | | 5/17/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 5/6/2005 | | 5/17/2005 | | PART |
Bill Alexander
|
|
|
1. The elevator shaft pits on the first floor is not located within a residential occupancy, but a "U-1" occupancy and shall be sprinklered per requirements of NFPA 13-8.14.5.1*. (BMC 7-01-50 -901.2)
2. Plans submitted are incomplete. Designer does not provide size of concealed spaces, attics, closets, and bathrooms or any small enclosures in which no sprinklers are to be installed. (NFPA 13R-6.1.7[9, 10])
Any assumption provided is not accepted. Revise and resubmit plans that meet requirements for verification of required fire protection. (BMC 7-01-50 -901.2)
3. Many restrooms which include showers and toilet spaces under this submittal will be considered part of the "restroom", since the designer does not address size or required separation on the plans. With lack of information, several restrooms on the 2nd and 3rd floors will require added fire sprinkler protection. Bathroom: Within a dwelling unit, any room or compartment containing a lavatory dedicated to personal hygiene, or a water closet, or bathing capability such as a shower or tub, or any combination of facilities thereof. A room is still considered a bathroom if it contains just a toilet. Bathroom compartments can be considered separate rooms provided they are enclosed with the required level of construction. (NFPA 13R-3.3.1*, A-3.3.1)
Any assumption provided is not accepted. Revise and resubmit plans that meet requirements for verification of required fire protection. (BMC 7-01-50 -901.2)
4. Manufacturer's data submittals provided for the Reliable Model F-1 Res 49 CCP Pendant, Reliable Model F3QR Q.R. Dry Pendant, and Reliable Model F1FR Q.R. sprinklers are all obsolete. Provide current manufacturers data submittals for all sprinkler heads submitting. (NFPA 13-3.3.1*)
5. Are the stair enclosures headed since you are installing residential heads in the same on the second and 3rd floors? Address this issue on the plans. (BMC 7-01-50 -901.2)
6. Residential sprinklers are currently listed for use under flat, smooth, horizontal ceilings. Sloped, beamed, and pitched ceilings could require special design features such as larger flows or a design for five or more sprinklers to operate in the compartment.
a. Has the designer verified slope/pitch requirements since it appears these heads are being installed outside there listing on the 3rd floor?
b.
c. Has the design spacing being measured on along the slope and not the floor, which means the actual floor coverage area will be less than the listed area.
Provide plans that address fire protection installation code and listed requirements issues and please reference Reliable's bulletin "035C" for correct listed installation practices.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/17/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/17/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/17/2005 | | 5/17/2005 | | DONE |
|
|
|
|
Telephone call | | | 5/17/2005 | | DONE |
|
|
|
called told brodie permit is ready and fees
|
Issue and Print Permit | | | 5/17/2005 | | DONE |
|
|
|
|
Application received | | | 5/6/2005 | | |
|
|
|
|