INSP-Final Inspection | 3/21/2006 | 3/22/2006 | 3/22/2006 | A | PASS |
Forrest France
|
|
|
c/n items have been completed, fire sprinkler permit passed inspection.
|
INSP-Final Inspection | 3/16/2006 | 3/17/2006 | 3/17/2006 | A | PART |
Forrest France
|
|
|
Items on previous correction notice have been completed, per state elevator requirements the wood framed sheetrocked shaft is considered combustible and will require a sprinkler at the top.
|
INSP-Final Inspection | 3/10/2006 | 3/16/2006 | 3/16/2006 | A | FAIL |
Forrest France
|
|
|
Missing escutcheons at some locations, provide flex coupling at riser, provide tags on riser, certify backflow preventer, sprinkler related alarms to be verified at next alarm inspection.
|
INSP-Final Inspection | 9/30/2005 | 9/30/2005 | 9/30/2005 | P | FAIL |
Forrest France
|
|
|
The resubmitted plans for field changes still do not match the installation as required, the first floor main and riser room locations are not accurate showing on opposite sides of the building from the actual install.
|
Telephone call | | | 9/23/2005 | | DONE |
|
|
|
Spoke with Brodie and told him permit is ready & fees///9/23/05 8:35am BAS
|
Issue permit | | | 9/23/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/30/2005 | | 9/22/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/22/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/22/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/22/2005 | | 9/22/2005 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 8/30/2005 | 8/31/2005 | 8/31/2005 | P | PART |
Forrest France
|
|
|
3rd floor (4 dormers) addition and full hydro test.
rick; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
Plan resubmittals received | | | 8/30/2005 | | |
|
|
|
|
INSP-Sprinkler Rough-in | 8/24/2005 | 8/25/2005 | 8/25/2005 | A | FAIL |
Forrest France
|
|
|
First floor piping does not match approved drawings due to several field changes that have been made, resubmit plans reflecting the actual installation for approval prior to field inspection, the second floor rough-in is good for cover, the third floor master bedrooms each have low soffits affecting proper coverage and response time.
|
INSP-Supply line flush | 6/30/2005 | 6/30/2005 | 6/30/2005 | P | CANC |
Forrest France
|
|
|
Wrong permit number called in, this inspection was for UG under permit fir04-00495.
|
INSP-Sprinkler Rough-in/Hydro | 6/30/2005 | 6/30/2005 | 6/30/2005 | P | CANC |
Forrest France
|
|
|
Wrong permit number called in, this inspection was for UG under permit fir04-00495.
|
CHANGE STATUS TO (ISS) | | | 6/30/2005 | | DONE |
|
|
|
|
(F) Reprint permit | | | 6/30/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 6/24/2005 | | 6/29/2005 | | PASS |
Bill Alexander
|
|
|
Modifications to undergroun on building #8.
R-2 Garage piping modified to protected CPVC.
|
Plan assigned to (Bill) | 6/24/2005 | | 6/29/2005 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/29/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/29/2005 | | DONE |
|
|
|
|
Telephone call | | | 6/29/2005 | | DONE |
|
|
|
tlk to brodie ###-#### that permit and fees are ready to picked up
|
Plan resubmittals received | | | 6/24/2005 | | |
|
|
|
|
Issue and Print Permit | | | 6/7/2005 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 5/26/2005 | | 6/6/2005 | | DONE |
Bill Alexander
|
|
|
|
Sprinkler Plan Check | 5/26/2005 | | 6/6/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/6/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/6/2005 | | DONE |
|
|
|
|
Telephone call | | | 6/6/2005 | | |
|
|
|
tlk to brodie ###-#### that permit and fees are ready to be picked up
|
Plan resubmittals received | | | 5/26/2005 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 5/6/2005 | | 5/17/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 5/6/2005 | | 5/17/2005 | | PART |
Bill Alexander
|
|
|
1. The elevator shaft pits on the first floor is not located within a residential occupancy, but a "U-1" occupancy and shall be sprinklered per requirements of NFPA 13-8.14.5.1*. (BMC 7-01-50 -901.2)
2. Plans submitted are incomplete. Designer does not provide size of concealed spaces, attics, closets, and bathrooms or any small enclosures in which no sprinklers are to be installed. (NFPA 13R-6.1.7[9, 10])
Any assumption provided is not accepted. Revise and resubmit plans that meet requirements for verification of required fire protection. (BMC 7-01-50 -901.2)
3. Many restrooms which include showers and toilet spaces under this submittal will be considered part of the "restroom", since the designer does not address size or required separation on the plans. With lack of information, several restrooms on the 2nd and 3rd floors will require added fire sprinkler protection. Bathroom: Within a dwelling unit, any room or compartment containing a lavatory dedicated to personal hygiene, or a water closet, or bathing capability such as a shower or tub, or any combination of facilities thereof. A room is still considered a bathroom if it contains just a toilet. Bathroom compartments can be considered separate rooms provided they are enclosed with the required level of construction. (NFPA 13R-3.3.1*, A-3.3.1)
Any assumption provided is not accepted. Revise and resubmit plans that meet requirements for verification of required fire protection. (BMC 7-01-50 -901.2)
4. Manufacturer's data submittals provided for the Reliable Model F-1 Res 49 CCP Pendant, Reliable Model F3QR Q.R. Dry Pendant, and Reliable Model F1FR Q.R. sprinklers are all obsolete. Provide current manufacturers data submittals for all sprinkler heads submitting. (NFPA 13-3.3.1*)
5. Are the stair enclosures headed since you are installing residential heads in the same on the second and 3rd floors? Address this issue on the plans. (BMC 7-01-50 -901.2)
6. Residential sprinklers are currently listed for use under flat, smooth, horizontal ceilings. Sloped, beamed, and pitched ceilings could require special design features such as larger flows or a design for five or more sprinklers to operate in the compartment.
a. Has the designer verified slope/pitch requirements since it appears these heads are being installed outside there listing on the 3rd floor?
b.
c. Has the design spacing being measured on along the slope and not the floor, which means the actual floor coverage area will be less than the listed area.
Provide plans that address fire protection installation code and listed requirements issues and please reference Reliable's bulletin "035C" for correct listed installation practices.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/17/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/17/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/17/2005 | | 5/17/2005 | | DONE |
|
|
|
|
Telephone call | | | 5/17/2005 | | DONE |
|
|
|
called told brodie permit ready and fees
|
Issue and Print Permit | | | 5/17/2005 | | DONE |
|
|
|
|
Application received | | | 5/6/2005 | | |
|
|
|
|
Sprinkler Plan Check | 8/30/2005 | | | | |
Bill Alexander
|
|
|
9/13/2005 - 12:30 PM Problem with revised desing (hydraulic verification). Also removed head in elevator (garage pit).
|