INSP-Final Inspection | 7/1/2005 | 7/1/2005 | 7/1/2005 | P | PASS |
Troy Cobbley
|
|
|
Fire sprinkler finaled
|
INSP-Alarm Testing | 6/30/2005 | 7/1/2005 | 7/1/2005 | A | PASS |
Troy Cobbley
|
|
|
Fire alarm finaled
|
INSP-Alarm Testing | 6/16/2005 | 6/17/2005 | 6/17/2005 | P | PART |
Forrest France
|
|
|
Two duct smoke detectors tested OK, horn/strobe locations and operation is satisfactory. Need to verify operation of preaction system under new programming, test smoke alarms, verify voltage drop.
|
Issue permit | | | 6/8/2005 | | |
|
|
|
|
Plan assigned to (Mary) | 5/18/2005 | | 6/7/2005 | | DONE |
|
|
|
|
Alarm Plan Check | | | 6/7/2005 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/7/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/7/2005 | | 6/7/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/7/2005 | | DONE |
|
|
|
|
Telephone call | | | 6/7/2005 | | DONE |
|
|
|
lft vm with rick groom that permit and fees are ready to be picked up
|
Telephone call | | | 6/3/2005 | | DONE |
|
|
|
Question regarding the battery calculations for 24 hour in lieu of 90 hour for FM deluge/pre-action.
|
Telephone call | | | 5/24/2005 | | DONE |
|
|
|
Left a message, need to get clarification on NAC circuits.
|
Application received | | | 5/18/2005 | | |
|
|
|
|
Case Summary | | | 5/18/2005 | | DONE |
|
|
|
|