INSP-Final Inspection | 2/14/2006 | 2/15/2006 | 2/15/2006 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 2/7/2006 | 2/7/2006 | 2/7/2006 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Dave Hannemans permission until issues with the shell building have been corrected.
|
INSP-Final Inspection | 2/2/2006 | 2/3/2006 | 2/3/2006 | P | FAIL |
Troy Cobbley
|
|
|
Provide approved hangers for th 4" main. Provide correct attachment for the eq bracing. Provide forward flush. Provide review comments. Provide correct air compressor and air maintenance device.
|
INSP-Sprinkler Rough-in | 1/25/2006 | 1/26/2006 | 1/26/2006 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler piping in the second floor attic and the east tenant improvement space are ok for cover
|
INSP-Sprinkler Rough-in | 1/17/2006 | 1/19/2006 | 1/19/2006 | A | PART |
Troy Cobbley
|
|
|
The south wing piping in the attic area is ok to cover with insulation
|
Issue and Print Permit | | | 1/9/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/30/2005 | | 1/6/2006 | | PASS |
Bill Alexander
|
|
|
|
Plan assigned to (Bill) | 12/30/2005 | | 1/6/2006 | | DONE |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/6/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/6/2006 | | 1/6/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/6/2006 | | DONE |
|
|
|
|
Telephone call | | | 1/6/2006 | | DONE |
|
|
|
tlk to tom easton ###-#### that permit and fees are ready to be picked up
|
INSP-Supply line flush | 1/4/2006 | 1/5/2006 | 1/5/2006 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
Telephone call | | | 1/5/2006 | | DONE |
|
|
|
lft vm for tom easton - ###-#### that permit failed and needs to be picked up
|
INSP-Supply line flush | 1/4/2006 | 1/4/2006 | 1/4/2006 | P | FAIL |
Troy Cobbley
|
|
|
united water did not show up
|
Plan resubmittals received | | | 12/30/2005 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in | 12/9/2005 | 12/12/2005 | 12/12/2005 | A | FAIL |
Troy Cobbley
|
|
|
No inspection is supposed to be called in but I did it anyway. Alot of changes have taken place with the piping. Per fitter these changes are reflected on another resubmittal that is in for review. This includes heads repiped and added in the second floor dry remote area, branchline added on the lower level dry system and main reroutes. Dry system heads dont meet 8.6.5.2.1.6 for spacing.
|
INSP-Sprinkler Rough-in | 11/22/2005 | 11/23/2005 | 11/22/2005 | P | CANC |
Troy Cobbley
|
|
|
No time for inspection
|
INSP-Sprinkler Rough-in | 11/21/2005 | 11/22/2005 | 11/22/2005 | A | CANC |
Troy Cobbley
|
|
|
No time for inspection
|
FIR-Aging Inspection | 9/8/2005 | 9/8/2005 | 9/13/2005 | | NR |
Troy Cobbley
|
|
|
Work is in progess. Job only has a partial approval. Resubmittals required.
|
Sprinkler Plan Check | 6/21/2005 | | 6/23/2005 | | PART |
Bill Alexander
|
|
|
12. Calculation problems Test Area #1: (June 22, 2005 - Area piping resubmittals required)
d. Line piping on the plans do not correlate with piping in the calcs. Revise and resubmit.
*June 22, 2005 - Provided corrections. Mains calculated for Area #1 incorporates 3" mains and plan show 2½". Mains through the riser Node point "10" shall be installed 3" (thinwall) minimum. Provide corrected resubmittal plans.
e. Nodes 7 to 8 includes an elevation pressure loss (riser) for 12'-0" and the plans show 15'-0"? Same node pipe lengths show 38'-10" yet the 15'-0" (riser) length was not included? Clarify and resubmit.
*June 22, 2005 - Not addressed. Clarify and resubmit.
f. Node 10 is nonexistent. Include clarification of the "5.197" psi increase from TOR to 10.
*June 22, 2005 - Not addressed. It is assumed as redlined on the plans which is impossible to determine since the riser is not dimensioned. Verify assumption location and resubmit.
13. Calculation problems Test Area #2:
c. Node 10 is nonexistent on the plans. Include clarification of the "5.197" psi increase from TOR to 10.
*June 22, 2005 - Not addressed. Provide clarification as also requested in item "12.d." above.
14. Calculation problems Test Area #3:
g. Node 10 is nonexistent on the plans.
*June 22, 2005 - Still missing. Reference item # "12.f." above.
|
Miscellaneous action | | | 6/23/2005 | | DONE |
|
|
|
Took plans & documents to front desk for distribution. 2nd review, no fee.
|
Telephone call | | | 6/23/2005 | | DONE |
|
|
|
lft ms with secretary for tom ###-#### that permit and fees are ready to be picked up
|
Plan resubmittals received | | | 6/21/2005 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/9/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/3/2005 | | 6/3/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/3/2005 | | DONE |
|
|
|
|
Telephone call | | | 6/3/2005 | | DONE |
|
|
|
tlk to tom easton that permit and fees are ready to be picked up
|
Plan assigned to (Bill) | 5/24/2005 | | 6/2/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 5/24/2005 | | 6/2/2005 | | PART |
Bill Alexander
|
|
|
The data has been moved to a Word document attached to this case.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/2/2005 | | DONE |
|
|
|
|
Application received | | | 5/24/2005 | | |
|
|
|
|