| INSP-Final Inspection | 11/21/2005 | 11/22/2005 | 11/22/2005 | A | PASS |
Forrest France
|
|
|
Correction notice items have been completed, submit as-builts reflecting pipe routing changes as required.
|
| INSP-Final Inspection | 11/16/2005 | 11/17/2005 | 11/17/2005 | A | PART |
Forrest France
|
|
|
Correction notice items have been completed, final pending forward flow, alarms, ceiling tile and canopies, and fill the annular space at UG penetration.
|
| INSP-Final Inspection | 11/15/2005 | 11/15/2005 | 11/15/2005 | P | FAIL |
Forrest France
|
|
|
Fail inspection due to numerous issues still not corrected, a 13 item c/n was left with Nick of Guho const., not all items inspected at this time-third floor not inspected as well.
|
| INSP-Final Inspection | 11/14/2005 | 11/14/2005 | 11/14/2005 | P | CANC |
Forrest France
|
|
|
Out of time, no inspection performed.
|
| Plan resubmittals received | | | 11/14/2005 | | PASS |
|
|
|
received 3 full sets of plans to provide a legible sheet FP-1 as noted 8/10/05 by BA. One plan set returned to contractor for insite/inspection.
|
| INSP-Final Inspection | 11/9/2005 | 11/10/2005 | 11/10/2005 | P | CANC |
Troy Cobbley
|
|
|
no time for inspection
|
| INSP-Supply line flush | 11/2/2005 | 11/3/2005 | 11/3/2005 | P | FAIL |
Forrest France
|
|
|
Provide resubmittals as required indicating information as requested on plan review notes and all field changes from original plans, overhead inspection failed due to numerous issues including spacing, head temps., bracing, seismic clearance, obstructions to discharge, riser not complete, etc., the UG was flush was performed and is acceptable.
|
| INSP-Sprinkler Rough-in/Hydro | 10/31/2005 | 11/1/2005 | 11/1/2005 | P | PART |
Forrest France
|
|
|
Overhead and underground hydrostatic tests are satisfactory.
|
| INSP-Sprinkler Rough-in/Hydro | 10/26/2005 | 10/28/2005 | 10/28/2005 | A | CANC |
Forrest France
|
|
|
No time available for this inspection today due to BODO projects.
|
| INSP-Sprinkler Rough-in | 9/8/2005 | 9/8/2005 | 9/8/2005 | P | PART |
Forrest France
|
|
|
The upright heads above hard lid areas on 2nd floor hall in front of the restrooms are okay to cover.
|
| Issue permit | | | 8/25/2005 | | DONE |
|
|
|
|
| Permit Ready to Issue | | | 8/11/2005 | | DONE |
|
|
|
|
| Sprinkler Plan Check | 7/28/2005 | | 8/10/2005 | | PART |
Bill Alexander
|
|
|
Plan FP-1 is not readable and is to poor a quality for archiving. Requested a corrected resumttal plan.
|
| Plan assigned to (Bill) | 7/28/2005 | | 8/10/2005 | | DONE |
|
|
|
|
| PLANS/APPL TAKEN TO FRONT DESK | | | 8/10/2005 | | DONE |
|
|
|
|
| Issue and Print Permit | | | 8/10/2005 | | DONE |
|
|
|
Partial-2nd review release. Contractor waited from 6/30/2005 till 8/10/2005 to obtain a valid permit, the same day that the third submittal was reviewed and returned to the permit desk. JWA
|
| Telephone call | | | 8/9/2005 | | DONE |
|
|
|
left mess that permit is ready
|
| Plan resubmittals received | | | 7/28/2005 | | DONE |
|
|
|
|
| Plan assigned to (Bill) | 6/2/2005 | | 6/30/2005 | | DONE |
|
|
|
|
| Sprinkler Plan Check | 6/27/2005 | | 6/30/2005 | | PART |
Bill Alexander
|
|
|
1. Addressing room identification is now missing on FP-2, pipe sizing and pipe dimensioning is not addressed (see detail below)? IFC Fire/Life Safety Inspector to verify Occupancy Use of room, minimum 1" pipe, required hanger, correct length of dry pendant, sealing of penetration, correct fitting connected to the dry pendant, room fire sprinkler spacing/coverage (obstructions from equipment coils, light fixtures, racks, shelving and etc.
2. First Floor Kitchen, scullery, basement, 2nd floor waitress (prep), basement storage (cooler, freezer), mechanical, cellar and other related storage (which might be considered OH-1 [reference NFPA 13-5.6.3.1, A.5.6.3.1, 12.1.10.1.1]), areas were piped the same as the light hazard use on the 2nd floor. Designer is not verifying a design providing correct densities (.15 gpm ft/2), combined with the areas of question. With a minimum 14.95 gpm flow for a minimum 7-psi, producing a .10 density per square foot, would not supply a 19.5 gpm flow at 7-psi required for a maximum 130-ft/2 spacing required for Ordinary Group 1 kitchen, storage, service areas, etc. It is also noted that all are not separated or verified on the plans as being separated from the light hazard use areas with 60 minute walls and 30 minute self closing doors. The maximum spacing this AHJ will allow for these OH-1 areas will be: 99-ft/2, of which some areas of protection still do not conform. Provide corrected plans and resubmit an approved protection design meeting all areas of the buildings use/hazards.
3. This riser needs some redesigning in order to meet minimum fire sprinkler installation requirements:
a. Riser will probably need an approved forward flow appurtenance and piping in order to meet the 330 gpm test flow through the backflow per requirements of 8.16.4.6.1*. If required flow is not produced through the main drain (addressed below in the "Testing & Verification" section) by the IFC Inspector, revised plans shall be provided for approval.
b. Extended system piping and control valve to permit FIR05-00266 "Boarding House" (also needing resubmittals) will require supervision/monitoring. This will entail relocation of this systems risers flow switch or the relocation of the "Boarding House" system risers flow switch to this location. Provide corrected plans that address correct system pipe monitoring and supervision. NOTE: These two structures have been considered 1 building under the IBC review and thus will be allowed 1 system riser. (NFPA 13-7.3.2.3.1)
c. Relocate FDC ball drip drain to its lowest point of piping for correct common sense draining purposes.
d. Address required flexible coupling at the base and top of the risers. (NFPA 13-9.3.2.3)
e. Provide a required inspectors test valve and include it on the plans. The test connection valve shall be readily accessible. The discharge shall be to the outside, to a drain connection capable of accepting full flow under system pressure, or to another location where water damage will not result. (NFPA 13-8.16.4.2.2, 8.16.4.2.3)
4. The system design is for Plan FP-1 requires redline corrections addressing identification occupancy use of all areas and rooms.
5. Any piping installed where ambient temperatures will drop below minimum 40ºF shall require corrections addressing an approved protection design and resubmitted for approval prior to installation.
14. Sidewall spray sprinklers shall be installed at the bottom of each elevator hoistway not more than 2'-0" above the floor of the pit. Correct elevator pit sprinkler. (NFPA 13-8.14.5.1*)
6. Where heat detectors are used to shut down elevator power prior to sprinkler operation, detectors shall have both a lower temperature rating and a higher sensitivity in comparison to the fire sprinkler. Provide clarification of elevator head temperature rating (coordinated with heat detector rating) on the plan FP-1. (NFPA 72-6.15.4.1*)
|
| PLANS/APPL TAKEN TO FRONT DESK | | | 6/30/2005 | | DONE |
|
|
|
|
| Inspection Record Card- Fire | 6/30/2005 | | 6/30/2005 | | DONE |
|
|
|
|
| Permit Ready to Issue | | | 6/30/2005 | | DONE |
|
|
|
|
| Telephone call | | | 6/30/2005 | | DONE |
|
|
|
lft ms with answering co for john ###-#### that permit and fees are ready to be picked up
|
| Plan resubmittals received | | | 6/27/2005 | | DONE |
|
|
|
|
| Sprinkler Plan Check | 6/2/2005 | | 6/9/2005 | | FAIL |
Bill Alexander
|
|
|
The data has been moved to a Word document attached to this case.
|
| Miscellaneous action | | | 6/9/2005 | | DONE |
|
|
|
Plans/documents returned to permit desk for calling and returning.
|
| Telephone call | | | 6/9/2005 | | DONE |
|
|
|
tlk to john warnick that permit has failed and needs to be picked up
|
| Telephone call | | | 6/9/2005 | | DONE |
|
|
|
commercial fire picked up failed plans on 6/9/05/mls
|
| Application received | | | 6/2/2005 | | |
|
|
|
|