| INSP-Final Inspection | 12/15/2005 | 12/15/2005 | 12/15/2005 | P | PASS |
Forrest France
|
|
|
c/n items are complete, fire sprinkler permit finaled.
|
| INSP-Sprinkler Rough-in/Hydro | 12/13/2005 | 12/14/2005 | 12/14/2005 | P | DONE |
Forrest France
|
|
|
This duplicate inspection already called in has been completed, see c/n items listed.
|
| INSP-Sprinkler Rough-in/Hydro | 12/13/2005 | 12/14/2005 | 12/14/2005 | A | PART |
Forrest France
|
|
|
Retest of the preaction system hydrostatic two hour test passed.
|
| INSP-Sprinkler Rough-in | 12/13/2005 | 12/14/2005 | 12/14/2005 | A | PART |
Forrest France
|
|
|
Overhead is acceptable pending installation of missing escutcheons, ceiling tile, remove tape and paper at uprights where covered for painting, need heads in head box and wrench, perform forward flow, alarms, sign at bell.
|
| INSP-Sprinkler Rough-in/Hydro | 12/13/2005 | 12/13/2005 | 12/13/2005 | P | FAIL |
Troy Cobbley
|
|
|
Pre-action hydro test failed.
|
| INSP-Sprinkler Rough-in/Hydro | 12/12/2005 | 12/13/2005 | 12/13/2005 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic test of the wet system passed inspection.
|
| INSP-Sprinkler Rough-in/Hydro | 12/12/2005 | 12/13/2005 | 12/13/2005 | A | PART |
Forrest France
|
|
|
The 24 hr. air test for the preaction system passed.
|
| INSP-Sprinkler Rough-in | 12/12/2005 | 12/12/2005 | 12/12/2005 | P | PART |
Forrest France
|
|
|
First floor overhead rough-in is okay for cover at the grid ceiling areas only, began 24 hour air test at 9:30 am at 42psi.
|
| CHANGE STATUS TO (ISS) | | | 12/9/2005 | | |
|
|
|
|
| Telephone call | | | 12/8/2005 | | DONE |
|
|
|
called ###-#### and told Jeff that permit is ready and fees
|
| Plan resubmittals received | | | 12/8/2005 | | DONE |
|
|
|
As-Built plan (1 set).
|
| Sprinkler Plan Check | 11/9/2005 | | 12/7/2005 | | PASS |
Bill Alexander
|
|
|
|
| Plan assigned to (Bill) | 11/9/2005 | | 12/7/2005 | | DONE |
Bill Alexander
|
|
|
|
| PLANS/APPL TAKEN TO FRONT DESK | | | 12/7/2005 | | DONE |
|
|
|
|
| Inspection Record Card- Fire | 12/7/2005 | | 12/7/2005 | | DONE |
|
|
|
|
| Permit Ready to Issue | | | 12/7/2005 | | DONE |
|
|
|
|
| INSP-Sprinkler Rough-in/Hydro | 12/1/2005 | 12/2/2005 | 12/2/2005 | A | PART |
Forrest France
|
|
|
2nd and 3rd floor only is okay for cover regarding rough-in, some sw and ssu heads are missing, various pendant heads are overspaced, sw heads are painted in some locations.
|
| INSP-Sprinkler Rough-in | 11/30/2005 | 12/1/2005 | 12/1/2005 | P | CANC |
Forrest France
|
|
|
Inspection to be rescheduled per agreement with Mike at ###-#### for 12/2 am.
|
| Plan resubmittals received | | | 11/9/2005 | | DONE |
|
|
|
|
| Permit Ready to Issue | | | 11/8/2005 | | DONE |
|
|
|
|
| Inspection Record Card- Fire | 11/8/2005 | | 11/8/2005 | | DONE |
|
|
|
|
| Telephone call | | | 11/8/2005 | | DONE |
|
|
|
Left message for Jeff Anderson that permit is ready & fees///11/8/05 9:05am BAS
|
| Issue and Print Permit | | | 11/8/2005 | | DONE |
|
|
|
|
| Plan assigned to (Bill) | 11/2/2005 | | 11/7/2005 | | DONE |
Bill Alexander
|
|
|
|
| PLANS/APPL TAKEN TO FRONT DESK | | | 11/7/2005 | | DONE |
|
|
|
|
| Permit Ready to Issue | | | 11/7/2005 | | DONE |
|
|
|
|
| Inspection Record Card- Fire | 11/7/2005 | | 11/7/2005 | | DONE |
|
|
|
|
| Sprinkler Plan Check | 11/2/2005 | | 11/7/2005 | | FAIL |
Bill Alexander
|
|
|
Resubmittal required addressing Review Comments:
2. Provide hydrant/fire sprinkler supply piping (details) which meets the minimum requirements of adopted codes. (BMC 7-01-50-901.2, IFC 105.4.2)
5. Designer provided a "cart blanc" data submittal on the preaction system:
2½" Supertrol Model H, D.I. Preaction Valve Assembly
2½" Supertrol D.I. Preaction Trim (option not identified)
Optional items installing:
Model 1 LAA-11T-M100X, 1/6 hp compressor w/2gal. Tank,
RP1001 Releasing Control Panel, (options not identified)
Alarm Annunciator,
Trouble Annunciator,
Smoke Detectors,
Pressure Maintenance Device
a. Trim package and Releasing Panel options were not identified. Provide clarification of packages incorporating.
b. It is assumed that Treasure Valley Fire Protection is including all other "options" addressed above. If any of the remaining options are not being installed, corrected submittals will be required addressing the changes.
(BMC 7-01-50-901.2, IFC 105.4.2)
16. All sectional details (reference 3 on FP-6) were not provided with dimensioning and/or not scaled. Architectural (A-5.3) plans included both? Provide dimensioning and/or scale for in sectional views for verification of elevations (hydraulic pressure losses). (BMC 7-01-50-901.2, IFC 105.4.2)
17. When resubmitting provided the correct fire permit and associated building permit numbers on the permit application.
|
| INSP-Sprinkler Rough-in | 11/3/2005 | 11/3/2005 | 11/3/2005 | P | PART |
Forrest France
|
|
|
The 3rd floor center common area hard lid area is acceptable for cover, also discussed coverage requirements for small room at perimeter and 2nd floor hard lid areas.
|
| Plan resubmittals received | | | 11/2/2005 | | PART |
Bill Alexander
|
|
|
|
| INSP-Sprinkler Rough-in | 10/7/2005 | 10/7/2005 | 10/7/2005 | P | FAIL |
Forrest France
|
|
|
Upright heads at first floor landings in both stairways are overspaced, upright head is missing above restroom 1st floor, hanger is missing on an armover above restroom 3rd floor, provide resubmittals reflecting added uprights and pipe layout changes at restrooms 1st, 2nd, and 3rd floors.
|
| INSP-Conference | 10/4/2005 | 10/4/2005 | 10/4/2005 | P | DONE |
Forrest France
|
|
|
On site discussion regarding sprinkler coverage requirements at stair landings and cloud ceiling areas.
|
| INSP-Sprinkler Rough-in/Hydro | 8/8/2005 | 8/9/2005 | 8/9/2005 | A | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic test for phase one and two of underground work passed inspection.
|
| INSP-Supply line flush | 8/8/2005 | 8/9/2005 | 8/9/2005 | A | PART |
Forrest France
|
|
|
Phase two UG fire supply line flush is satisfactory.
|
| INSP-Supply line flush | 8/8/2005 | 8/8/2005 | 8/8/2005 | P | CANC |
Forrest France
|
|
|
Cancel inspection per Sam, not ready, will reschedule for tomorrow.
|
| INSP-Sprinkler Rough-in/Hydro | 8/8/2005 | 8/8/2005 | 8/8/2005 | P | CANC |
Forrest France
|
|
|
Cancel inspection per Sam with Treasure Valley Sprinkler.
|
| Inspection Record Card- Fire | 8/4/2005 | | 8/4/2005 | | DONE |
|
|
|
|
| Permit Ready to Issue | | | 8/4/2005 | | |
|
|
|
|
| Telephone call | | | 8/4/2005 | | DONE |
|
|
|
left mess that permit is ready
|
| Issue and Print Permit | | | 8/4/2005 | | DONE |
|
|
|
|
| Plan assigned to (Bill) | 6/30/2005 | | 8/3/2005 | | DONE |
|
|
|
|
| Sprinkler Plan Check | 7/25/2005 | | 8/3/2005 | | PART |
Bill Alexander
|
|
|
1. No details addressing the connection of this hydrant to a supply which is secondary fire protection to the primary, fire sprinklers. Provide hydrant/fire sprinkler supply piping (details) which meets the minimum requirements of adopted codes. (BMC 7-01-50-901.2, IFC 105.4.2)
2. a. Trim package and Releasing Panel options were not identified. Provide clarification of packages invorproating.
b. It is assumed that Treasure Valley Fire Protection is including all other "options" addressed above. If any of the remaining options are not being installed, corrected submittals will be required addressing the changes.
3. Submittals are incomplete. The working plan submittal shall include the manufacturer's installation instructions/information for any specialty equipment, including descriptions, applications, and limitations, devices, etc. Provide data submittal on the manufacturers "electric risers" (if applicable), with model identified and referenced. If not incorporating this electric type risers, provide clearer details of a typical floor zone control incorporating in this building which includes all required devices and appurtenance. (BMC 7-01-50-901.2, IFC 105.4.2, NFPA 13-14.1.4)
4. All sectional details (reference 3 on FP-6) were not provided with dimensioning and/or not scaled. Architectural (A-5.3) plans included both? Provide dimensioning and/or scale for in sectional views for verification of elevations (hydraulic pressure losses). (BMC 7-01-50-901.2, IFC 105.4.2)
5. When resubmitting provided the correct fire permit and associated building permit numbers on the permit application.
|
| PLANS/APPL TAKEN TO FRONT DESK | | | 8/3/2005 | | DONE |
Bill Alexander
|
|
|
|
| Sprinkler Plan Check | 6/30/2005 | | 7/11/2005 | | FAIL |
Bill Alexander
|
|
|
The data has been moved to a Word document attached to this case.
|
| Miscellaneous action | | | 7/11/2005 | | DONE |
|
|
|
8:05 am, took failed plans/documents to permit desk for returning and corrections.
|
| Telephone call | | | 7/11/2005 | | DONE |
|
|
|
tlk to jeff anderson that his permit has failed and to picked up
|
| Application received | | | 6/30/2005 | | |
|
|
|
|