(AHRENS & DEANGELI - US BANK BUILDING - STE 300) To relocate and add fire sprinkler protection for the creation, by expansion of a tenant space into an adjacent area located on the 3rd floor for a total of 5,513-ft/2 office tenant space, in an existing high-rise building. Fire sprinkler work is related to selective nonstructural demolition, new interior nonbearing walls and suspended ceilings. The fire sprinkler system shall comply with NFPA 13 as regulated by the Fire Department. This building is fire sprinklered because it is a high-rise. This fire protection work shall comply with the IFC 2003 and the permit review comments; each regulated by the Fire Chief. The review comments, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD05-01435.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/26/20057/26/20057/26/2005PPASS
DetailsTroy Cobbley
Fire sprinkler finaled
INSP-Final Inspection7/25/20057/26/20057/26/2005AFAIL
DetailsTroy Cobbley
See approved plans for areas where the sprinkler pendants are still overspaced.
INSP-Sprinkler Rough-in7/22/20057/25/20057/25/2005PCANC
DetailsTroy Cobbley
Todd said they are not ready for inspection
INSP-Final Inspection7/22/20057/22/20057/22/2005PFAIL
DetailsForrest France
A sprinkler head is not installed or shown on plans in a closet at the NE corner, missing hanger at arm over in office north side, heads in several offices on the west side are overspaced from adjacent walls, no further items inspected at this time. Contractor to re-schedule inspection when ready.
Issue and Print Permit  7/12/2005 DONE
Plan assigned to (Bill)6/30/2005 7/11/2005 DONE
Sprinkler Plan Check6/30/2005 7/11/2005 PASS
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  7/11/2005 DONE
Inspection Record Card- Fire7/11/2005 7/11/2005 DONE
Permit Ready to Issue  7/11/2005 DONE
Telephone call  7/11/2005 DONE
lft ms with secretary ###-#### that permit and fees are ready
Application received  6/30/2005