INSP-Final Inspection | 9/2/2005 | 9/2/2005 | 9/2/2005 | P | PASS |
Forrest France
|
|
|
Fire alarm finaled.
|
INSP-Final Inspection | 8/31/2005 | 9/1/2005 | 9/1/2005 | A | DEFR |
Forrest France
|
|
|
This inspection to be performed by Mary Froemke due to scheduling conflicts.
|
INSP-Final Inspection | 8/30/2005 | 8/31/2005 | 8/31/2005 | A | FAIL |
Forrest France
|
|
|
The strobe in the confrence room is mounted too low for code requirements, duct smoke detectors tested okay, no other items inspected.
|
INSP-Final Inspection | 8/30/2005 | 8/30/2005 | 8/30/2005 | P | CANC |
Forrest France
|
|
|
No time for inspection, Grant will reschedule for tomorrow per our conversation.
|
INSP-Final Inspection | 8/26/2005 | 8/29/2005 | 8/29/2005 | P | NR |
Forrest France
|
|
|
Cancel inspection per Grant with Protex, not ready for inspection.
|
Override - Parcel Holds | | | 7/11/2005 | | |
|
|
|
|
Override - Parcel Holds | | | 7/11/2005 | | |
|
|
|
|
Inspection Record Card- Fire | 7/11/2005 | | 7/11/2005 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 7/11/2005 | | |
|
|
|
|
Permit Ready to Issue | | | 7/11/2005 | | |
|
|
|
|
Telephone call | | | 7/11/2005 | | DONE |
|
|
|
tlk to rob ahten ###-#### that permit and fees are ready to be picked up
|
Override - Parcel Holds | | | 7/11/2005 | | |
|
|
|
|
Issue and Print Permit | | | 7/11/2005 | | DONE |
|
|
|
|
Plan assigned to (Mary) | 7/7/2005 | | 7/8/2005 | | DONE |
|
|
|
|
Alarm Plan Check | | | 7/8/2005 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/8/2005 | | DONE |
|
|
|
|
Telephone call | | | 7/7/2005 | | DONE |
|
|
|
Resubmittal required because the voltage drop calculations on circuit #13 are incorrect. Talked to Terry, she'll let Rob know, I said I would give 2 days before I deny them.
|
Application received | | | 7/6/2005 | | |
|
|
|
|
Case Summary | | | 7/6/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/11/2005 | | | | |
|
|
|
|