Permit Information
Permit NumberFIR05-00396
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 12550 W EXPLORER DR
Project NameSPR ALPINE BUILDING
Customer Number 
ePlanReview 
Description
ALPINE BUILDING (SHELL & CORE) - To install a complete overhead, standard spray, quick response sprinklers, for light hazard occupancy use, fire sprinkler system in a new 22,315-ft/2, two story, (1st floor 11,525-ft/2, 2nd floor 10,790-ft/2), concrete tilt-up office shell and core building. Fire sprinkler include finish work related to core area restrooms and janitor's closets on the first and second floors, entry and hallways, mechanical room and elevator machine room on the first floor, elevator and stairways. Separate tenant improvement permits will be required to finish this building for occupancy. The 2003 International Building Code, Section 1019, Exception #9 is being used as an alternate to the 2000 International Building Code, Section 1005.3.2 to allow two open stairways in a fully sprinklered building. The underground fire service supply was permitted by the same contractor under FIR05-00248. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD05-002346.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/29/200512/30/200512/30/2005PPASS
DetailsTroy Cobbley
permit finaled
INSP-Final Inspection12/30/200512/30/200512/30/2005PPASS
DetailsTroy Cobbley
permit finaled
INSP-Alarm Testing12/28/200512/29/200512/29/2005PFAIL
DetailsTroy Cobbley
Plug sprinkler heads mounted horizontally in the T.I. space. Reinstall the ball drip at the FDC. Certify the backflow preventor. Relocate the bell to the FDC. Provide above ground hydro test papers.
INSP-Alarm Testing12/27/200512/28/200512/29/2005APASS
DetailsTroy Cobbley
The interconnection of the fire sprinkler devices and the fire alarm panel passed. I went over outstanding issues on the fire sprinkler system with Mike
INSP-Sprinkler Rough-in12/16/200512/19/200512/19/2005PDEFR
DetailsForrest France
Wrong permit number called in, this inspection was for the related TI work on the second floor rough-in for cover.
INSP-Sprinkler Rough-in/Hydro12/5/200512/7/200512/7/2005PPART
DetailsTroy Cobbley
Sprinkler rough-in passed for the most part. Heads are overspaced at the top of stairs 209 and in the restrooms. Maximum head spacing 120sq. ft. Riser piping not inspected with this overhead inspection.
Issue and Print Permit  11/21/2005  
Sprinkler Plan Check11/18/2005 11/18/2005 PASS
DetailsTroy Cobbley
Plans approved.
PLANS/APPL TAKEN TO FRONT DESK  11/18/2005 DONE
Inspection Record Card- Fire11/18/2005 11/18/2005 DONE
Permit Ready to Issue  11/18/2005  
Telephone call  11/18/2005  
tlk to trent bice ###-#### that permit and fees are ready to be picked up
INSP-Sprinkler Rough-in10/4/200510/5/200510/5/2005AFAIL
DetailsTroy Cobbley
Resubmittals required per the review comments. No inspection performed.
Inspection Record Card- Fire8/26/2005 8/26/2005 DONE
Permit Ready to Issue  8/26/2005 DONE
Telephone call  8/26/2005 DONE
tlk to trent bice that permit and fees are ready to be picked up
Issue and Print Permit  8/26/2005 DONE
Sprinkler Plan Check8/15/2005 8/25/2005 PART
DetailsBill Alexander
1. Unless approved otherwise by the code official (Fire Chief), sprinkler systems in any building 2 or more levels in height shall be separated by floor control assemblies in addition to main control and alarm features. Floor control assembly components shall include, but not be limited to, properly placed and installed control valve, alarming device, test and. drain assembly, and pressure gage. Provide plans that meet this requirement or provide justification to the Fire Chief why it is impossible. (BMC 7-01-55 IFC 903.1.5, IFC 105.4.2)
July 27, 2005 - Revised plan is unacceptable. First floor (zone) control is not separated from the 2nd floor (zone) control. Revise and resubmit.
August 25, 2005 - Plan resubmittals riser detail appears to show one riser control in the fire sprinkler riser room. Outside this fire sprinkler control room, approximately 7'-0" to the west, is a tee with another riser control which feeds up to the second floor. Through the same tee horizontally is another riser control for the 1st floor. If this is the intent, why does the designer put both floor zone controls outside the sprinkler riser room? These riser controls will require accessing and draining to outside the building both for pipe and inspectors test draining. These control valves and drains shall be accessible from the floor! This design does not address this accessibility as addressed in NFPA 13-8.1.2*, 8.15.1.1.1.1, 8.16.4.2.2. If modifications will affect the calculations to an extent where the most demanding area is affected by a 3# loss, then revised plans and calcs shall also be resubmitted for verification. (BMC 7-01-55 IFC 903.1.5, IFC 105.4.2)

2. Plan FP2, 1st floor "Restrooms" are overspaced/obstructed (per design). Revise and resubmit.
August 25, 2005 - No changes found. IFC Inspector shall verify maximum distance off one wall, multiplied twice with maximum distance off the other multiplied twice, which shall not exceed the maximum design verified (for that floor). Another issue is the (blind) entry wall and sink inset wall. This means there may be problem with blind spots in coverage. Fire sprinkler protection in buildings that are required to be fully fire sprinklered does not have exceptions to areas as addressed. Reference FP2 Red Lines. Revise and resubmit.

3. Plan FP2, 1st floor northeast of full height entry wall is overspaced. Revised and resubmit.
August 25, 2005 - No changes found. IFC Inspector shall verify maximum distance off one wall, multiplied twice with maximum distance off the other multiplied twice, which shall not exceed the maximum design verified (for that floor). Another issue is the (blind) entry wall and sink inset wall. This means there may be problem with blind spots in coverage. Fire sprinkler protection in buildings that are required to be fully fire sprinklered does not have exceptions to areas as addressed. Reference FP2 Red Lines. Revise and resubmit.

4. Plan FP2, 1st floor mechanical room (maximum allowed is 98.5-ft/2.
August 25, 2005 - No changes found. IFC Inspector shall verify maximum distance off one wall, multiplied twice with maximum distance off the other multiplied twice, which shall not exceed the maximum design verified (for that floor). Another issue is the (blind) entry wall and sink inset wall. This means there may be problem with blind spots in coverage. Fire sprinkler protection in buildings that are required to be fully fire sprinklered does not have exceptions to areas as addressed. Reference FP2 Red Lines. Revise and resubmit.

5. Calculation Area #2 (First Floor), page #2 is missing. Resubmit for system verification.

6. Calculation Area #2, (First Floor) Elevation pressure loss found is only 2'-0". Head analysis indicates 13'-6", unless the information is in the missing sheet addressed in item #25 above? Verify and resubmit.

7. Include nodes used in the calculations corresponding with the same on the plans (riser, etc.).
PLANS/APPL TAKEN TO FRONT DESK  8/25/2005 DONE
Stamped one set for site partial approval only.
Plan assigned to (Bill)7/7/2005 8/25/2005 DONE
Plan resubmittals received  8/15/2005 DONE
Sprinkler Plan Check7/19/2005 7/27/2005 FAIL
DetailsBill Alexander
July 27, 2005 - Resubmittal Review and Corrections Required (which shall include item #4 in the first review):
1. Plan FP2 piping and calculation provided from nodes FF to D1 do not correlate correctly. Revise and resubmit.

2. Plan FP1 and calculations from nodes SRC to FF do not match. Provide underground plan that match calculations.

3. Identify (occupancy) the 4 rooms on each building corner plan FP2.

4. Plan FP2, First Floor (both) stairs open or have access beneath? Provide plans that clarify construction and/or protection with resubmittals.

5. Plan FP2, second level protection over "Stair #209" area is overspaced. Revise and resubmit.

6. Plan FP2, 1st floor "Restrooms" are overspaced (per design). Revise and resubmit.

7. Plan FP2, 1st floor area where sprinkler off Node "A1" east to full height entry area is overspaced. Revise and resubmit.

8. Plan FP2, 1st floor northeast of full height entry wall is overspaced. Revised and resubmit.

9. Plan FP2, 1st floor mechanical room (maximum allowed is 98.5-ft/2.

10. Plan FP2, 1st floor areas west of the mechanical room is overspaced. Revise and resubmit.

11. Plan FP2, 2nd floor coverage of (1st floor) entry is overspaced. Revise and resubmit.

12. Plan FP2, 2nd floor sprinkler located northwest of elevator is overspaced to the south. Revise and resubmit.

13. Plan FP2, needs clarification of 2nd floor wall heights on the plan prior to continuing review.

NOTE: Calculations on the 1st floor have not been reviewed. Designer shall verify design with all plans and calculations prior to submitting.
Miscellaneous action  7/27/2005 DONE
Returned (failed) documents (less 1 copy) to the permit desk for calling and returning.
Telephone call  7/27/2005 DONE
left mess for trent that plans failed & no fee
Plan resubmittals received  7/19/2005 DONE
Sprinkler Plan Check7/7/2005 7/14/2005 FAIL
DetailsBill Alexander
Miscellaneous action  7/14/2005 DONE
Returned plans/submittals to permit desk for corrections.
Telephone call  7/14/2005 DONE
tlk to trent bice - ###-#### that permit failed needs to be picked up
Application received  7/7/2005