INSP-Final Inspection | 6/14/2006 | 6/14/2006 | 6/15/2006 | P | PASS |
Forrest France
|
|
|
Fire sprinkler passed final inspection, permit finaled.
|
INSP-Sprinkler Rough-in | 5/1/2006 | 5/2/2006 | 5/2/2006 | P | PASS |
Forrest France
|
|
|
The remainder of overhead work for this permit is good for cover, project is ready for final when all ceiling tile is installed.
|
INSP-Final Inspection | 12/12/2005 | 12/12/2005 | 12/12/2005 | P | NR |
Forrest France
|
|
|
Project is not complete, next phase which includes work under this permit has not started.
|
INSP-Sprinkler Rough-in/Hydro | 12/12/2005 | 12/12/2005 | 12/12/2005 | P | PART |
Forrest France
|
|
|
Overhead rough-in is satisfactory for work installed, area as circled on approved plans is not complete or inspected at this time.
|
Plan assigned to (Bill) | 7/7/2005 | | 7/18/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 7/8/2005 | | 7/18/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/18/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/18/2005 | | 7/18/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/18/2005 | | DONE |
|
|
|
|
Telephone call | | | 7/18/2005 | | |
|
|
|
tlk to brodie stenquist ###-#### that permit and fees are ready to be picked up
|
Issue permit | | | 7/18/2005 | | DONE |
|
|
|
|
Application received | | | 7/7/2005 | | |
|
|
|
|