Permit Information
Permit NumberFIR05-00405
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 2444- 2450 N BOGUS BASIN RD
Project NameSPR HIGHLANDS VILLAGE BLD 13
Customer Number 
ePlanReview 
Description
HIGHLANDS VILLAGE BLD #13, HARRISON FLOOR PLAN TYPE * 2444, 2448, 2446 & 2450 N. Bogus Basin Rd. To install overhead fire sprinkler protection throughout a new 10,716-ft/2, three story, four unit apartment building. The first floor is 3,806-ft/2 which 2,000-ft/2 is for the garages (protected to Ordinary Group design), the second floor is 3,946-ft/2 and the third floor is 2,964-ft/2 (Light Hazard design). Three units are three bedroom and three and one half baths, one unit is four bedroom and three and one half baths. This building is fire sprinklered per NFPA 13-R. The fire sprinkler system work shall comply with the IFC 2000, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work. The underground fire service supply was installed under FIR04-00174. This permit is attached to building permit: BLD04-00949.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/11/20064/11/20064/11/2006PPASS
DetailsForrest France
Required corrections are complete, permit finaled.
INSP-Final Inspection4/10/20064/11/20064/11/2006ANR
DetailsForrest France
Permit not ready for final pending project related alarm work.
INSP-Final Inspection3/31/20064/3/20064/3/2006APART
DetailsForrest France
Heads blocked by surface mounted lights have been moved, some escutcheons are not installed, performed forward flow, final pending testing of sprinkler related alarms and supervisory conditions.
INSP-Final Inspection3/30/20063/30/20063/30/2006PFAIL
DetailsTroy Cobbley
Sprinkler heads are blocked by light fixtures. Heads need to be atleast 20" away from side of fixture. No other items inspected.
INSP-Sprinkler Rough-in11/3/200511/3/200511/3/2005PPART
DetailsForrest France
Insulation tenting at 3rd floor is acceptable, okay to cover, "blown in" insulation to be done after lid is sheetrocked.
INSP-Sprinkler Rough-in/Hydro10/6/200510/6/200510/6/2005PPART
DetailsForrest France
Overhead hydrostatic test passed inspection.
INSP-Sprinkler Rough-in10/3/200510/3/200510/3/2005PPART
DetailsForrest France
Overhead rough-in is good for cover on the 1st and 2nd floors only, a head is required in the 3rd floor master closet as it exceeds 24 sq ft, need to inspect tenting and insulation on the 3rd floor when installed before cover, heads at furnace/water heater need appropriate temp. rating.
Issue and Print Permit  7/21/2005 DONE
Telephone call  7/19/2005 DONE
left mess that permit is ready
Plan assigned to (Bill)7/8/2005 7/18/2005 DONE
Sprinkler Plan Check7/8/2005 7/18/2005 PASS
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  7/18/2005 DONE
Inspection Record Card- Fire7/18/2005 7/18/2005 DONE
Permit Ready to Issue  7/18/2005 DONE
Application received  7/8/2005