INSP-Final Inspection | 3/10/2006 | 3/10/2006 | 3/10/2006 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 3/9/2006 | 3/10/2006 | 3/10/2006 | A | PART |
Forrest France
|
|
|
All areas inspected are satisfactory, final pending replacement of one painted head in the restroom (see enlarged detail E for location), and installation of missing escutcheons at the restroom and office area at the end of the NE wing.
|
INSP-Final Inspection | 3/8/2006 | 3/9/2006 | 3/9/2006 | P | DEFR |
Forrest France
|
|
|
No time for this inspection today, to be rescheduled per conversation with contractor for 3/10 in the am.
|
INSP-Final Inspection | 3/3/2006 | 3/6/2006 | 3/6/2006 | A | NR |
Forrest France
|
|
|
Per phone conversation with Brad of TVFP the project is not ready for inspection at this time.
|
Plan resubmittals received | | | 3/3/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 3/3/2006 | | 3/3/2006 | | PASS |
|
|
|
Plan Modifciation affecting scope of work changes.
|
INSP-Sprinkler Rough-in | 9/29/2005 | 9/30/2005 | 9/30/2005 | A | PART |
Forrest France
|
|
|
Relocated heads in storage room 132, EQ bracing in corridor, and head at north entry vestibule are acceptable.
|
Sprinkler Plan Check | 9/19/2005 | | 9/19/2005 | | PASS |
Troy Cobbley
|
|
|
Plan Modification 9/19/2005 - Existing SSU's in Storage Room 132 relocated to meet code. Upright sprinkler heads are being removed from Corridor 217,216,215,214 and 213 due to sheet rock being installed. See modified plans which are to be inserted into the previously issued set.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/19/2005 | | DONE |
Troy Cobbley
|
|
|
|
Inspection Record Card- Fire | 9/19/2005 | | 9/19/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/19/2005 | | DONE |
|
|
|
|
Telephone call | | | 9/19/2005 | | DONE |
|
|
|
called ###-#### and told Brad permit ready to pick up and no fees
|
CHANGE STATUS TO (ISS) | | | 9/19/2005 | | DONE |
|
|
|
no fee previously issued
|
Plan resubmittals received | | | 9/6/2005 | | |
|
|
|
|
INSP-Sprinkler Rough-in | 8/11/2005 | 8/11/2005 | 8/12/2005 | P | PART |
Troy Cobbley
|
|
|
Sprinkler rough-in as shown on the city plans is ok. Pendant head at north entry into large room needs to match existing. Earth quake bracing is lacking in the north end. Per the approved plans, Design Hazard/Limitiations, this permit shall meet the minimum requirements of the International FIre Code. The entire sprinkler system shall meet the code requirements under which it was installed and if it doesn't it must be brought up to current code. This is for all aspects of the sprinkler system including but not limited to hangers, EQ bracing and sprinkler spacing.
|
Issue and Print Permit | | | 7/27/2005 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 7/18/2005 | | 7/26/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 7/18/2005 | | 7/26/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/26/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/26/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/26/2005 | | 7/26/2005 | | DONE |
|
|
|
|
Telephone call | | | 7/26/2005 | | DONE |
|
|
|
tlk to brad bettencourt ###-#### that permit and fees are ready to be picked up
|
Case Summary | | | 7/18/2005 | | DONE |
|
|
|
|
Application received | | | 7/18/2005 | | |
|
|
|
|