INSP-Final Inspection | 8/17/2005 | 8/17/2005 | 8/17/2005 | P | PASS |
Forrest France
|
|
|
Fire sprinkler finaled.
|
INSP-Sprinkler Rough-in | 8/4/2005 | 8/5/2005 | 8/5/2005 | A | PART |
Forrest France
|
|
|
Sprinkler rough-in is okay to cover, will final permit when all ceiling tile and escutcheons are installed.
|
INSP-Sprinkler Rough-in | 8/3/2005 | 8/3/2005 | 8/3/2005 | P | PART |
Forrest France
|
|
|
Overhead rough-in for fire sprinkler is good for cover except one location at a pendent head near a column in the open area to which the arm over has been supported by a ceiling grid wire from the deck, the pipe shall have an approved and listed hanger installed prior to final.
|
Issue permit | | | 7/27/2005 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 7/18/2005 | | 7/26/2005 | | DONE |
|
|
|
|
Miscellaneous action | | | 7/26/2005 | | DONE |
|
|
|
9:00am. De Best requested to swap this permit review with BoDo #8 FIR05-00425.
|
Sprinkler Plan Check | 7/18/2005 | | 7/26/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/26/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/26/2005 | | 7/26/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/26/2005 | | DONE |
|
|
|
|
Telephone call | | | 7/26/2005 | | DONE |
|
|
|
tlk to randy bowron ###-#### that permit and fees are ready to be picked up
|
Application received | | | 7/18/2005 | | |
|
|
|
|