INSP-Final Inspection | 9/7/2005 | 9/7/2005 | 9/7/2005 | P | PASS |
Forrest France
|
|
|
Fire sprinkler finaled.
|
INSP-Sprinkler Rough-in | 8/29/2005 | 8/30/2005 | 8/30/2005 | A | PART |
Forrest France
|
|
|
Overhead rough-in is good for cover, can final permit when ceiling tile with escutcheons are installed.
|
(F) Reprint permit | | | 8/23/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/12/2005 | | 8/22/2005 | | PASS |
Bill Alexander
|
|
|
|
Miscellaneous action | | | 8/22/2005 | | DONE |
|
|
|
Took approved revised plans to permit desk for returning.
|
Telephone call | | | 8/22/2005 | | DONE |
|
|
|
tlk to brad bettencourt ###-#### that permit and fees are ready to be picked up
|
Plan resubmittals received | | | 8/12/2005 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in | 8/11/2005 | 8/11/2005 | 8/11/2005 | P | FAIL |
Troy Cobbley
|
|
|
The existing sidewall heads above the ceiling are blocked by new duct work. Additional heads and resubmittals are required. I told the contractor that I was ok with the school opening as long as this work area was not accessible.
|
Issue and Print Permit | | | 8/2/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/2/2005 | | 8/2/2005 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 7/22/2005 | | 8/1/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 7/22/2005 | | 8/1/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/1/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/1/2005 | | 8/1/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/1/2005 | | DONE |
|
|
|
|
Telephone call | | | 8/1/2005 | | DONE |
|
|
|
lft ms with secretary that permit and fees are ready to be picked up
|
Application received | | | 7/22/2005 | | |
|
|
|
|