INSP-Final Inspection | 2/27/2006 | 3/2/2006 | 3/2/2006 | A | PASS |
Forrest France
|
|
|
Fire alarm passed inspection.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/9/2005 | | DONE |
|
|
|
|
Issue and Print Permit | | | 8/9/2005 | | DONE |
|
|
|
|
Plan assigned to (Mary) | 7/28/2005 | | 8/8/2005 | | DONE |
|
|
|
|
Alarm Plan Check | | | 8/5/2005 | | PASS |
|
|
|
Require a revised "Scope of Work" prior to inspection for clarification for the PDS Fire Inspector.
Approved pending PDS Fire Inspector field verification. No written comments.
|
Application received | | | 7/28/2005 | | |
|
|
|
|