INSP-Final Inspection | 4/22/2010 | 4/23/2010 | 4/26/2010 | P | PASS |
Forrest France
|
|
|
Corrections field verified for completion, inspection passed, fire sprinkler permit finaled.
|
INSP-Final Inspection | 4/5/2010 | 4/7/2010 | 4/7/2010 | A | FAIL |
Forrest France
|
|
|
Meeting on site to determine status of the permit work. Refer to activity comments completed 8/30/05 for necessary corrections to be made prior to permit final.
|
Miscellaneous action | | | 3/12/2010 | | DONE |
|
|
|
Sent email requesting project status.
|
INSP-Sprinkler Rough-in | 8/26/2005 | 8/30/2005 | 8/30/2005 | A | FAIL |
Forrest France
|
|
|
The installed SW heads are quick response and do not match the standard response SW heads as submitted on the city approved documents for this project.
|
Plan assigned to (Bill) | 8/3/2005 | | 8/15/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/3/2005 | | 8/15/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/15/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/15/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/15/2005 | | 8/15/2005 | | DONE |
|
|
|
|
Telephone call | | | 8/15/2005 | | DONE |
|
|
|
Spoke with Tom that permit is ready & fees///8/15/05 1:55pm BAS
|
Issue and Print Permit | | | 8/15/2005 | | DONE |
|
|
|
|
Application received | | | 8/3/2005 | | |
|
|
|
|