INSP-Final Inspection | 2/6/2007 | 2/7/2007 | 2/7/2007 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. Inspection was performed by Brian Johnson
|
INSP-Final Inspection | 2/6/2007 | 2/6/2007 | 2/6/2007 | P | FAIL |
Troy Cobbley
|
|
|
Per Brian the first floor and second floors are now complete. Third and fourth floors will be started tomorrow.
|
INSP-Final Inspection | 2/5/2007 | 2/5/2007 | 2/5/2007 | A | FAIL |
Troy Cobbley
|
|
|
The remaining areas of the first floor were tested by Brian today except for the east elevator. See the city approved plans for locations of deficiencies.
|
INSP-Final Inspection | 2/1/2007 | 2/2/2007 | 2/2/2007 | A | FAIL |
Troy Cobbley
|
|
|
The north elevator was all that was tested today.
|
INSP-Final Inspection | 1/31/2007 | 2/1/2007 | 2/1/2007 | A | FAIL |
Troy Cobbley
|
|
|
Items tested today include the facp and three nac panels on the first floor. Also tested are all of the sprinkler devices.
|
Alarm Plan Check | 11/6/2006 | | 11/6/2006 | | PEND |
|
|
|
Resubmittal # 6; this plan review is a modification to the approved plan drawings previously issued. The plan review conducted were those items clouded as revision #5 only. A comparison of the original approved drawings and drawing modification should be conducted on site. This review is pending field Inspection results.
|
Inspection Record Card- Fire | 11/6/2006 | | 11/6/2006 | | DONE |
|
|
|
|
(F) Reprint permit | | | 11/6/2006 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/25/2006 | | DONE |
|
|
|
|
FIR-Aging Inspection | 4/11/2006 | 4/11/2006 | 4/11/2006 | | NR |
Troy Cobbley
|
|
|
Work is in progress
|
Permit Ready to Issue | | | 1/10/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/10/2006 | | 1/10/2006 | | DONE |
|
|
|
|
Issue and Print Permit | | | 1/10/2006 | | DONE |
|
|
|
|
Alarm Plan Check | | | 1/9/2006 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/9/2006 | | DONE |
|
|
|
|
Miscellaneous action | | | 1/9/2006 | | DONE |
|
|
|
NOTE TO PDS FIRE INSPECTOR: A resubmittal is required prior to final inspection.
|
Plan resubmittals received | | | 12/28/2005 | | |
|
|
|
|
Alarm Plan Check | | | 12/27/2005 | | FAIL |
|
|
|
Resubmittal required for the voltage drop calculations.
|
Plan resubmittals received | | | 12/13/2005 | | DONE |
|
|
|
Received fax with responses to the comments.
|
Telephone call | | | 12/12/2005 | | DONE |
|
|
|
Request to Charlie Bayne, to submit written responses for the comments dated 9/28 and 11/18.
|
Plan resubmittals received | | | 12/6/2005 | | |
|
|
|
|
Case Summary | | | 12/6/2005 | | DONE |
|
|
|
|
Alarm Plan Check | | | 11/18/2005 | | FAIL |
|
|
|
Requested the emergency electrical system information from Charlie Bayne, as per comment #2.
|
Plan resubmittals received | | | 11/4/2005 | | DONE |
|
|
|
Received clouded prints
|
Miscellaneous action | | | 11/1/2005 | | DONE |
|
|
|
Phoned Charlie Bayne. The resubmittal has not been "clouded", I explained to him that I don't have time to go back and check all 15 pages of the submittal. He will get it resolved (clouded).
|
Plan resubmittals received | | | 10/19/2005 | | DONE |
|
|
|
|
Alarm Plan Check | | | 9/28/2005 | | FAIL |
|
|
|
Resubmittal required. Faxed comments to Ronnie Zahm.
|
Plan resubmittals received | | | 9/14/2005 | | |
|
|
|
|
Alarm Plan Check | | | 8/15/2005 | | FAIL |
|
|
|
Resubmittal required. Faxed comments to Ronnie Zahm.
|
Plan resubmittals received | | | 8/9/2005 | | |
|
|
|
Changed out the sheet with the matrix. Omitted the FA tie in of the single station smoke detectors.
|
Case Summary | | | 8/5/2005 | | DONE |
|
|
|
|
Application received | | | 8/5/2005 | | |
|
|
|
|
Plan assigned to (Mary) | 8/5/2005 | | | | |
|
|
|
|