INSP-Final Inspection | 12/8/2005 | 12/8/2005 | 12/8/2005 | P | PASS |
Forrest France
|
|
|
UG supply line finaled.
|
INSP-Final Inspection | 12/7/2005 | 12/7/2005 | 12/7/2005 | P | PASS |
Forrest France
|
|
|
UG fire supply line finaled.
|
INSP-Supply line flush | 11/18/2005 | 11/21/2005 | 11/21/2005 | A | PART |
Forrest France
|
|
|
UG fire supply line flush performed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 11/18/2005 | 11/21/2005 | 11/21/2005 | A | PART |
Forrest France
|
|
|
UG hydrostatic test passed within the allowable leakage allowance per NFPA.
|
INSP-Final Inspection | 11/9/2005 | 11/9/2005 | 11/9/2005 | P | PART |
Forrest France
|
|
|
UG fire supply line is acceptable to cover pending verification and approval of field modifications from original approved plans via resubmittals.
|
INSP-Sprinkler Rough-in | 10/14/2005 | 10/17/2005 | 10/17/2005 | A | FAIL |
Forrest France
|
|
|
The riser and stub out appear to be installed in a satisfactory manner, however no city stamped approved plans were available on site to confirm or verify the install.
|
Plan assigned to (Bill) | 8/10/2005 | | 8/18/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/10/2005 | | 8/18/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/18/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/18/2005 | | 8/18/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/18/2005 | | DONE |
|
|
|
|
Telephone call | | | 8/18/2005 | | DONE |
|
|
|
called told Don permit is ready and fees
|
Issue and Print Permit | | | 8/18/2005 | | DONE |
|
|
|
|
Application received | | | 8/10/2005 | | |
|
|
|
|