INSP-Final Inspection | 11/2/2005 | 11/2/2005 | 11/2/2005 | P | PASS |
Forrest France
|
|
|
Fire sprinkler finaled.
|
INSP-Final Inspection | 11/1/2005 | 11/1/2005 | 11/1/2005 | P | FAIL |
Forrest France
|
|
|
Sprinkler head in the "sterile room 107" is overspaced.
|
INSP-Sprinkler Rough-in/Hydro | 10/27/2005 | 10/28/2005 | 10/28/2005 | A | PASS |
Troy Cobbley
|
|
|
Still need ceiling tile and canopies in some locations. Corrections as noted on plans corrected. Hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 10/24/2005 | 10/25/2005 | 10/25/2005 | A | PART |
Troy Cobbley
|
|
|
Sprinkler piping is ok to cover. See city approved plans for locations of deficiencies which include hydraulic calculations due to an additional head added in a pocket
|
Issue and Print Permit | | | 8/25/2005 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 8/12/2005 | | 8/19/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/12/2005 | | 8/19/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/19/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/19/2005 | | 8/19/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/19/2005 | | DONE |
|
|
|
|
Telephone call | | | 8/19/2005 | | DONE |
|
|
|
left mess that permit is ready
|
Application received | | | 8/12/2005 | | |
|
|
|
|