Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberFIR05-00523
StatusFinaled
Name SIMPLEX/GRINNELL
Site Address 247 N MILWAUKEE ST
Project NameSPR JARED GALLERIA OF JEWELRY
Customer Number 
ePlanReview 
Description
(JARED THE GALLERIA OF JEWELRY) To remove all Central Model "A" 5.6 K-factor standard spray standard response SSP's and install 69 Tyco Series "TY-FRB," Q.R., SSP, 8.0 K-factor, in the existing remodel of a 7,013-ft/2 retail sales building (6,015-ft/2 ground floor and 998-ft/2 mezzanine) for a new retail jewelry store. The existing yard P.I.V. will be removed and a new W.P.I.V. will be installed which includes system riser modifications. The fire sprinkler work is related to include interior nonbearing walls and suspended ceiling. The upright 5.6 K-factor, standard spray standard response sprinkler will remain. This building is fully fire sprinklered. This fire protection work shall comply with the IFC 2003 and the permit review comments; each regulated by the Fire Chief. The review comments, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD05-01455.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/16/200511/17/200511/17/2005PPASS
DetailsTroy Cobbley
Fire sprinkler finaled
INSP-Final Inspection11/14/200511/15/200511/15/2005AFAIL
DetailsTroy Cobbley
Provide 200 degree pendant at main entrance that is next to the supply grill.
INSP-Sprinkler Rough-in11/9/200511/10/200511/10/2005ACANC
DetailsTroy Cobbley
no time for inspection
INSP-Final Inspection11/9/200511/10/200511/10/2005ACANC
DetailsTroy Cobbley
no time for inspection
Permit Ready to Issue  11/9/2005 DONE
Inspection Record Card- Fire11/9/2005 11/9/2005 DONE
Issue and Print Permit  11/9/2005 DONE
Plan assigned to (Bill)10/14/2005 11/9/2005 DONE
DetailsBill Alexander
Plan resubmittals received  11/9/2005 DONE
Sprinkler Plan Check11/9/2005 11/9/2005 PASS
DetailsBill Alexander
Anti-freeze system.
PLANS/APPL TAKEN TO FRONT DESK  11/9/2005 DONE
Telephone call  11/8/2005 DONE
Called on 11-8-05 @ 4:16 by BAS - pick up failed plans
Sprinkler Plan Check10/14/2005 11/8/2005 FAIL
DetailsBill Alexander
1. Anti-freeze calculations do not match pipe installing, which includes node locations, etc., etc. Reference NFPA 13 Chapter 13 & 14 and resubmit addressing minimum requirements for correlation of plans and calcs. This was addressed in Item #5, which is now critical and will be required. (BMC 7-01-50:901.2, IFC 105.4)

2. Verify, clarify and install peak heads in overbuild meeting minimum installation codes addressed in NFPA 13 Chapter 8 Section 6.
INSP-Sprinkler Rough-in/Hydro11/3/200511/4/200511/4/2005APASS
DetailsTroy Cobbley
Anti-freeze hydro test passed.
INSP-Sprinkler Rough-in/Hydro11/2/200511/3/200511/3/2005AFAIL
DetailsTroy Cobbley
Anti-freeze loop hydro test failed twice today.
INSP-Final Inspection11/1/200511/2/200511/3/2005PCANC
DetailsTroy Cobbley
jim paige; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
INSP-Sprinkler Rough-in/Hydro11/1/200511/2/200511/2/2005ACANC
DetailsTroy Cobbley
Canceled hydro since anti-freeze system would hold 200lbs.
Miscellaneous action  10/31/2005 DONE
Approved a written request from SimplexGrinnell for early start to install the antifreeze system prior to approval of the resubmitted the plan modification (original plans did not include an AF system for the combustible concealed spaces). I denied their request for a TOC; that request will have to be considered separately after the sprinkler installation has been installed and satisfactorily inspected.
INSP-Sprinkler Rough-in/Hydro10/18/200510/19/200510/19/2005APASS
DetailsTroy Cobbley
Overhead hydro test passed.
INSP-Sprinkler Rough-in10/17/200510/18/200510/18/2005APASS
DetailsTroy Cobbley
Piping above the lay-in ceiling tiles is ok to cover except for the new anti-freeze system piping which has not been approved yet. Also the restrooms in the southwest corner are not to be covered until the new uprigth sprinklers are inspected.
Plan resubmittals received  10/14/2005 DONE
INSP-Sprinkler Rough-in/Hydro9/15/20059/16/20059/16/2005PPART
DetailsTroy Cobbley
Hard lid areas as marked on the plans are ok to cover.
Issue permit  9/2/2005  
Plan assigned to (Bill)8/18/2005 9/1/2005 DONE
Sprinkler Plan Check8/18/2005 9/1/2005 PASS
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  9/1/2005 DONE
Inspection Record Card- Fire9/1/2005 9/1/2005 DONE
Permit Ready to Issue  9/1/2005  
Telephone call  9/1/2005 DONE
lft vm with tom easton ###-#### that permit and fees are ready to be picked up
Application received  8/18/2005